6378 W 79TH ST 90045
Certificate Information: 6378 W 79TH ST 90045
- Application / Permit
- 24016-10000-23833
- Plan Check / Job No.
- B24LA15142
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODEL ON 1ST AND 2ND FLOOR OF (E) 2-STORY SFD TO ENLARGE KITCHEN, CREATE (N) LAUNDRY, CREATE (N) BATHROOM, AND REMODEL BATHROOMS. EXTEND FRONT ENTRY PORCH. WORK DONE PER ENGINEER DESIGN.
- Permit Issued
- Issued on 10/24/2024
- Issuing Office
- Current Status
- CofO Issued on 12/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/30/2024 | KAMYAR EMAMI |
| Corrections Issued | 7/31/2024 | KAMYAR EMAMI |
| Applicant returned to address corrections | 8/15/2024 | ROSENDO MEDINA |
| Applicant returned to address corrections | 8/27/2024 | ROSENDO MEDINA |
| Plan Check Approved | 9/10/2024 | MADISON O'DELL |
| Issued | 10/24/2024 | APPLICANT |
| CofO in Progress | 12/1/2025 | ANTHONY EGSON |
| Permit Finaled | 12/12/2025 | RICHARD STEINBACH |
| CofO Issued | 12/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 12/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/2/2024 | VASIL MIHALEV |
| ZA Case | Cleared | 8/16/2024 | DAVID URITA |
| Specific Plan | Cleared | 9/6/2024 | JOSHUA JONES |
Contact Information
| Contractor | Wards American Building Concepts Inc; Lic. No.: 754779-B | , |
| Engineer | Melchor,, Oscar Elias; Lic. No.: NA76828 | , |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 3/20/2025 | Approved | RUBEN RIVAS |
| HVAC-Rough | 3/20/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 3/20/2025 | Corrections Issued | RUBEN RIVAS |
| Special/Order Compliance | 3/20/2025 | Partial Inspection | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/25/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Rough | 3/25/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Deputy Wood Construction | 3/26/2025 | Conditional Approval | RUBEN RIVAS |
| PLUMBING-Rough | 3/26/2025 | Partial Approval | RUBEN RIVAS |
| Special/Order Compliance | 3/26/2025 | Partial Inspection | BOBBY KEY |
| Interior/Exterior Lathing | 4/2/2025 | Corrections Issued | RUBEN RIVAS |
| Interior/Exterior Lathing | 4/7/2025 | Partial Approval | RUBEN RIVAS |
| Interior/Exterior Lathing | 4/9/2025 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 4/17/2025 | Approved | RUBEN RIVAS |
| Green Building Rough | 4/17/2025 | Approved | RUBEN RIVAS |
| Insulation | 4/17/2025 | Approved | RUBEN RIVAS |
| PLUMBING-Rough | 4/17/2025 | Approved | RUBEN RIVAS |
| Drywall Nailing | 4/23/2025 | Approved | JAYLIN GRAVITTE |
| Interior/Exterior Lathing | 5/6/2025 | Approved | RUBEN RIVAS |
| Shower Pan | 5/6/2025 | Approved | RUBEN RIVAS |
| ELECTRICAL-Final | 11/12/2025 | Corrections Issued | RUBEN RIVAS |
| HVAC-Final | 11/12/2025 | Corrections Issued | RUBEN RIVAS |
| PLUMBING-Final | 11/12/2025 | Partial Approval | RUBEN RIVAS |
| ELECTRICAL-Final | 11/18/2025 | Approved | RUBEN RIVAS |
| HVAC-Final | 11/18/2025 | Approved | RUBEN RIVAS |
| Final | 11/26/2025 | OK to Issue CofO | ANTHONY EGSON |
| Green Building Final | 11/26/2025 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 11/26/2025 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 11/26/2025 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 11/26/2025 | Approved | ANTHONY EGSON |