124 N AVENUE 63 90042
Certificate Information: 124 N AVENUE 63 90042
- Application / Permit
- 24016-10000-23676
- Plan Check / Job No.
- B24LA14924
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN. CONVERT EXISTING 2 STORY ACCESSORY LIVING QUARTERS W/ ATT GARAGE TO NEW ACCESSORY DWELLING UNIT W/ ATT GARAGE PER GCS 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d) AND (g).
- Permit Issued
- Issued on 9/19/2024
- Issuing Office
- Current Status
- CofO Issued on 1/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/26/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/29/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 7/30/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 9/6/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 9/16/2024 | KAMYAR EMAMI |
| Plan Check Approved | 9/18/2024 | KAMYAR EMAMI |
| Issued | 9/19/2024 | APPLICANT |
| CofO in Progress | 12/20/2024 | ALIZAH MAYAGOITIA |
| Permit Finaled | 1/3/2025 | DEROLD HAUFF |
| CofO Issued | 1/3/2025 | DEROLD HAUFF |
| Permit Finaled | 1/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/1/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 8/1/2024 | AMBER CAMPBELL |
| "Q" conditions | Cleared | 8/5/2024 | JASON CHAN |
| CPC | Cleared | 8/5/2024 | JASON CHAN |
| Eng Process Fee Ord 176,300 | Cleared | 8/28/2024 | AMBER CAMPBELL |
| HPOZ | Cleared | 8/28/2024 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 8/28/2024 | LAMBERT GIESSINGER |
| Miscellaneous | Cleared | 8/28/2024 | LAMBERT GIESSINGER |
| Miscellaneous | Cleared | 8/28/2024 | LAMBERT GIESSINGER |
| ZI | Cleared | 8/28/2024 | LAMBERT GIESSINGER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 11/26/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 11/26/2024 | Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 11/26/2024 | Approved | ALIZAH MAYAGOITIA |
| Final | 12/17/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Final | 12/20/2024 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Service/Power Release | 12/20/2024 | Approved | ALIZAH MAYAGOITIA |