3839 S BERRYMAN AVE 90066

Certificate Information: 3839 S BERRYMAN AVE 90066

Application / Permit
24016-10000-23530
Plan Check / Job No.
B24LA14666
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) GARAGE TO DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d)
Permit Issued
Issued on 5/8/2025
Issuing Office
Current Status
Issued on 5/8/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/30/2024 APPLICANT
Assigned to Plan Check Engineer 8/2/2024 CARLOS MONTES
Corrections Issued 8/3/2024 CARLOS MONTES
Applicant returned to address corrections 9/9/2024 CARLOS MONTES
Plan Check Approved 12/16/2024 CARLOS MONTES
Issued 5/8/2025 APPLICANT

Permit Application Clearance Information

Specific Plan Cleared 8/22/2024 HAMID GHAEMMAGHAMI
Address approval Cleared 9/5/2024 LIAM ODONOVAN
Sewer availability Cleared 9/5/2024 LIAM ODONOVAN
Eng Process Fee Ord 176,300 Cleared 9/7/2024 LIAM ODONOVAN
Construction near power lines Cleared 12/9/2024 RIDWAN HARDY

Contact Information

Architect , ; Lic. No.: C36439       ,
Contractor New Bear Wind Inc; Lic. No.: 1059216-B       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/14/2025 Corrections Issued MICHAEL ALLEN
Sewer 5/14/2025 Partial Approval MICHAEL ALLEN
Pre-Inspection 6/10/2025 Approved MICHAEL ALLEN
Sewer 6/10/2025 Approved MICHAEL ALLEN
Excavation/Setback/Form/Re-Bar 6/27/2025 Approved RUBEN RIVAS
Floor/Roof Diaphrgm/Shear Wall 9/9/2025 Corrections Issued JESUS PINEDA
Wood Frame 10/6/2025 Corrections Issued RUBEN RIVAS
ELECTRICAL-Rough 10/28/2025 Approved WILBER ROSALES
Floor/Roof Diaphrgm/Shear Wall 10/28/2025 Partial Approval WILBER ROSALES
HVAC-Rough 10/28/2025 Not Ready for Inspection WILBER ROSALES
PLUMBING-Rough 10/28/2025 Approved WILBER ROSALES
BUILDING-Rough-Frame 12/11/2025 Partial Approval WILBER ROSALES
HVAC-Rough 12/11/2025 Partial Approval WILBER ROSALES
Interior/Exterior Lathing 12/11/2025 Partial Approval WILBER ROSALES
HVAC-Rough 12/26/2025 Not Ready for Inspection WILBER ROSALES
Insulation 12/26/2025 Partial Approval WILBER ROSALES
ELECTRICAL-Rough 1/7/2026 No Access for Inspection WILBER ROSALES
HVAC-Rough 1/7/2026 No Access for Inspection WILBER ROSALES
Insulation 1/7/2026 No Access for Inspection WILBER ROSALES
Wood Frame 1/7/2026 No Access for Inspection WILBER ROSALES
Footing/Foundation/Slab 1/14/2026 Approved ANTHONY EGSON
Green Building Rough 1/14/2026 Not Ready for Inspection ANTHONY EGSON
HVAC-Rough 1/14/2026 Partial Approval ANTHONY EGSON
BUILDING-Rough-Frame 1/28/2026 Corrections Issued MICHAEL ALLEN
BUILDING-Rough-Frame 2/27/2026 Corrections Issued DAKOTA LOW
Insulation 2/27/2026 Not Ready for Inspection DAKOTA LOW
BUILDING-Rough-Frame 3/6/2026 Approved DAKOTA LOW
Floor/Roof Diaphrgm/Shear Wall 3/6/2026 Approved DAKOTA LOW
Green Building Rough 3/6/2026 Approved DAKOTA LOW
HVAC-Rough 3/6/2026 Approved DAKOTA LOW
Insulation 3/6/2026 Approved DAKOTA LOW
Drywall Nailing 3/25/2026 Approved DAKOTA LOW