1308 1/2 W 80TH ST 90044

Certificate Information: 1308 1/2 W 80TH ST 90044

Application / Permit
24016-10000-23522
Plan Check / Job No.
B24LA14645
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: Convert an Existing Garage and an Unpermitted dwelling into ADU. Information Bulletin/Public-Building Code reference no: 2023 LARC, DOCUMENT NO P/BC 2023-150 ACCESSORY DWELLING UNITS-CONVERSIONS, UNPERMITTED BUILDINGS OR UNPERMITTED ADU's" was the guideline for design and getting the dwelling up to code.
Permit Issued
Issued on 12/15/2024
Issuing Office
Current Status
CofO Issued on 4/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2024 APPLICANT
Assigned to Plan Check Engineer 7/26/2024 PINANK PATEL
Corrections Issued 8/2/2024 PINANK PATEL
Applicant returned to address corrections 9/5/2024 MOHAMMAD ESMAILI
Applicant returned to address corrections 9/16/2024 PINANK PATEL
Applicant returned to address corrections 10/9/2024 PINANK PATEL
Plan Check Approved 12/11/2024 PINANK PATEL
Issued 12/15/2024 APPLICANT
CofO in Progress 4/27/2026 SABAS ALONSO
Permit Finaled 4/30/2026 DEROLD HAUFF
CofO Issued 4/30/2026 DEROLD HAUFF
Permit Finaled 4/30/2026 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 8/15/2024 ALEXIS SCHULTZ
Address approval Cleared 9/26/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 9/26/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 9/30/2024 WALLIE JONG
Sewer availability Cleared 9/30/2024 WALLIE JONG
Community Plan Implem. Overlay Cleared 10/3/2024 MANERI ROMAN
Construction near power lines Cleared 12/9/2024 RIDWAN HARDY
Construction within easement Cleared 12/9/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/5/2025 Partial Inspection JOHN QUINTANILLA
Pre-Inspection 6/20/2025 Corrections Issued FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 8/1/2025 Corrections Issued LUIS CASTRO
Excavation/Setback/Form/Re-Bar 8/7/2025 Not Ready for Inspection JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 8/12/2025 Partial Approval JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 8/26/2025 Conditional Approval SALVADOR MARTINEZ
Excavation/Setback/Form/Re-Bar 8/28/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 9/26/2025 Approved SALVADOR MARTINEZ
Special/Order Compliance 9/26/2025 Corrections Issued SALVADOR MARTINEZ
Interior/Exterior Lathing 10/7/2025 Partial Inspection JOHN QUINTANILLA
Interior/Exterior Lathing 10/14/2025 Corrections Issued DEVON JACKSON
Interior/Exterior Lathing 10/20/2025 Partial Approval ANTHONY RAMOS
Wood Frame 12/18/2025 Partial Inspection JOHN QUINTANILLA
Insulation 12/30/2025 Approved JOHN QUINTANILLA
Wood Frame 12/30/2025 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 1/6/2026 Approved JOHN QUINTANILLA
Drywall Nailing 1/8/2026 Approved ALEX COLIN
Interior/Exterior Lathing 2/3/2026 Approved JOHN QUINTANILLA
Final 3/16/2026 Corrections Issued JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 3/16/2026 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 3/16/2026 Approved JOHN QUINTANILLA
Final 4/23/2026 OK to Issue CofO SABAS ALONSO