2844 W AVENUE 33 90065

Certificate Information: 2844 W AVENUE 33 90065

Application / Permit
24016-10000-23494
Plan Check / Job No.
B24LA14608
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing 547 sf detached storage to ADU per state law. (E) attached garage to remain
Permit Issued
Issued on 9/9/2024
Issuing Office
Current Status
CofO Issued on 8/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2024 APPLICANT
Assigned to Plan Check Engineer 7/26/2024 JOSEPH RAFOLS
Corrections Issued 7/26/2024 JOSEPH RAFOLS
Applicant returned to address corrections 8/21/2024 ALEXANDER JOO
Plan Check Approved 9/4/2024 SHANGQIN XIE
Issued 9/9/2024 APPLICANT
CofO in Progress 8/13/2025 NICHOLAS LOPEZ
CofO in Progress 8/13/2025 NICHOLAS LOPEZ
CofO in Progress 8/13/2025 NICHOLAS LOPEZ
Permit Finaled 8/15/2025 DEROLD HAUFF
CofO Issued 8/15/2025 DEROLD HAUFF
Permit Finaled 8/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/7/2024 CELINA MORENO
Sewer availability Cleared 8/7/2024 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 8/8/2024 CELINA MORENO
Supp. Use District POD/CDO/TDO Cleared 8/15/2024 ANDREA MAGANA-WITHERS
Construction near power lines Cleared 8/26/2024 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/12/2025 Conditional Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 2/20/2025 Partial Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 2/20/2025 Approved THOMAS LOGRASSO
PLUMBING-Rough 2/20/2025 Partial Approval THOMAS LOGRASSO
Sewer 2/28/2025 Approved NICHOLAS LOPEZ
Wood Frame 2/28/2025 Partial Approval NICHOLAS LOPEZ
Interior/Exterior Lathing 3/12/2025 Partial Approval BRENDAN MORELLI
ELECTRICAL-Rough 3/24/2025 Corrections Issued NICHOLAS LOPEZ
Floor/Roof Diaphrgm/Shear Wall 3/24/2025 Approved NICHOLAS LOPEZ
HVAC-Rough 3/24/2025 Approved NICHOLAS LOPEZ
PLUMBING-Rough 3/24/2025 Approved NICHOLAS LOPEZ
Underground Mechanical 3/24/2025 Corrections Issued NICHOLAS LOPEZ
BUILDING-Rough-Frame 3/26/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Rough 3/26/2025 Approved NICHOLAS LOPEZ
Green Building Rough 3/26/2025 Approved NICHOLAS LOPEZ
MERV13>=Rough 3/26/2025 Approved NICHOLAS LOPEZ
Underground Mechanical 3/26/2025 Approved NICHOLAS LOPEZ
Insulation 4/3/2025 Conditional Approval REGINA MENDEZ
Drywall Nailing 4/8/2025 Approved NICHOLAS LOPEZ
Interior/Exterior Lathing 4/8/2025 Approved NICHOLAS LOPEZ
Final 5/29/2025 Corrections Issued NICHOLAS LOPEZ
MERV13>=Final 5/29/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 5/29/2025 SGSOV No Gas NICHOLAS LOPEZ
Smoke Detectors 5/29/2025 Approved NICHOLAS LOPEZ
Final 8/8/2025 Conditional Approval NICHOLAS LOPEZ
Final 8/13/2025 OK to Issue CofO NICHOLAS LOPEZ
Service/Power Release 8/13/2025 Approved NICHOLAS LOPEZ