2519 S SHENANDOAH ST 90034

Certificate Information: 2519 S SHENANDOAH ST 90034

Application / Permit
24016-10000-23447
Plan Check / Job No.
B24LA14568
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A). **FIRE SPRINKLERED THROUGHOUT
Permit Issued
Issued on 1/3/2025
Issuing Office
Current Status
CofO Issued on 10/7/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2024 APPLICANT
Assigned to Plan Check Engineer 7/26/2024 DANIEL ABRAMYAN
Corrections Issued 7/27/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 8/26/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 9/21/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 10/1/2024 ISIS ARGUETA
Applicant returned to address corrections 10/17/2024 ISIS ARGUETA
Applicant returned to address corrections 11/26/2024 DANIEL ABRAMYAN
Plan Check Approved 12/31/2024 ROSENDO MEDINA
Issued 1/3/2025 APPLICANT
CofO in Progress 10/1/2025 EVAN COOPER
Permit Finaled 10/7/2025 RICHARD STEINBACH
CofO Issued 10/7/2025 RICHARD STEINBACH
Permit Finaled 10/7/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 7/30/2024 DAVID LOPEZ
Sewer availability Cleared 7/30/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 8/8/2024 JEANIE LAM
Construction near power lines Cleared 11/25/2024 RIDWAN HARDY
Construction within easement Cleared 11/25/2024 RIDWAN HARDY

Contact Information

Contractor Dreams Renovation Inc; Lic. No.: 1101893-B       ,
Engineer Howe,, Carl William; Lic. No.: C44773 4358 SEPULVEDA BLVD      CULVER CITY, CA 90230

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/24/2025 Corrections Issued MEL KHACHATOURIAN
Deputy Drilled-In Anchors 1/28/2025 Approved SEAN HAUPT
Excavation/Setback/Form/Re-Bar 1/28/2025 Approved SEAN HAUPT
ELECTRICAL-Rough 2/4/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Partial Approval EVAN COOPER
HVAC-Rough 2/4/2025 Approved EVAN COOPER
PLUMBING-Rough 2/4/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 3/7/2025 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 3/11/2025 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 3/11/2025 Partial Approval EVAN COOPER
Insulation 3/18/2025 Partial Approval ARAM AVEDISIAN
Insulation 3/19/2025 Approved EVAN COOPER
BUILDING-Rough-Frame 3/21/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/21/2025 Approved EVAN COOPER
Drywall Nailing 4/1/2025 Approved EVAN COOPER
Interior/Exterior Lathing 4/1/2025 Approved EVAN COOPER
PLUMBING-Rough 4/1/2025 Corrections Issued EVAN COOPER
Shower Pan 4/1/2025 Approved EVAN COOPER
ELECTRICAL-Final 6/5/2025 Approved EVAN COOPER
Final 6/5/2025 Corrections Issued EVAN COOPER
HVAC-Final 6/5/2025 Approved EVAN COOPER
PLUMBING-Final 6/5/2025 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 6/5/2025 SGSOV Approved EVAN COOPER
Smoke Detectors 6/5/2025 Approved EVAN COOPER
Final 9/30/2025 OK to Issue CofO EVAN COOPER