2442 S COLBY AVE 90064

Certificate Information: 2442 S COLBY AVE 90064

Application / Permit
24016-10000-23426
Plan Check / Job No.
B24LA14543
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: Convert the detached storage room into a NEW ADU w/ addition "COMPLY WITH DEPARTMENT ORDER effective date 09/11/2024. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 11/6/2024
Issuing Office
Current Status
Issued on 11/6/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/23/2024 APPLICANT
Assigned to Plan Check Engineer 7/26/2024 JOHN MESIAS
Corrections Issued 7/29/2024 JOHN MESIAS
Applicant returned to address corrections 10/24/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 11/1/2024 NEHEMIAS RAMOS
Plan Check Approved 11/5/2024 NEHEMIAS RAMOS
Issued 11/6/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/2/2024 DARIN LAM
Sewer availability Cleared 8/2/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 8/5/2024 DARIN LAM
ZI Cleared 8/5/2024 YINGSHI HUANG
ZI Cleared 8/5/2024 YINGSHI HUANG
Specific Plan Cleared 8/28/2024 RICHARD WOO
Construction near power lines Cleared 10/21/2024 ENRIQUE ACOSTA
Roof/Waste drainage to street Cleared 11/4/2024 DARIN LAM

Contact Information

Architect Woodcraft,, Lawrence Albert; Lic. No.: NA23651       ,
Contractor Owner-Builder       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Insulation 12/5/2024 Not Ready for Inspection RYAN BARNES
ELECTRICAL-Rough 3/26/2025 Approved RYAN BARNES
PLUMBING-Rough 3/26/2025 Corrections Issued RYAN BARNES
BUILDING-Rough-Frame 4/2/2025 Partial Approval RYAN BARNES
Insulation 4/2/2025 Approved RYAN BARNES
PLUMBING-Rough 4/2/2025 Approved RYAN BARNES
BUILDING-Rough-Frame 4/15/2025 Approved JOHN MATTILLO
Green Building Rough 4/15/2025 Approved JOHN MATTILLO
MERV13>=Rough 4/15/2025 Approved JOHN MATTILLO
Drywall Nailing 4/18/2025 Approved JOHN MATTILLO
PLUMBING-Rough 4/25/2025 Approved RYAN BARNES
Interior/Exterior Lathing 5/1/2025 Conditional Approval RYAN BARNES
HVAC-Final 7/10/2025 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 10/7/2025 SGSOV Not Ready RYAN BARNES
Pre-Inspection 10/10/2025 Not Ready for Inspection RYAN BARNES
Final 10/17/2025 Not Ready for Inspection ANDREW BEELI
Footing/Foundation/Slab 10/17/2025 Not Ready for Inspection ANDREW BEELI
Green Building Final 10/17/2025 Not Ready for Inspection ANDREW BEELI
MERV13>=Final 10/17/2025 Not Ready for Inspection ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 10/17/2025 SGSOV Not Ready ANDREW BEELI
Smoke Detectors 10/17/2025 Not Ready for Inspection ANDREW BEELI
Final 10/28/2025 Conditional Approval RYAN BARNES
Footing/Foundation/Slab 10/28/2025 Approved RYAN BARNES
Green Building Final 10/28/2025 Approved RYAN BARNES
MERV13>=Final 10/28/2025 Approved RYAN BARNES
SGSOV-Seismic Gas S/O Valve 10/28/2025 SGSOV Approved RYAN BARNES
Smoke Detectors 10/28/2025 Approved RYAN BARNES