2211 S GRAND AVE 90731
Certificate Information: 2211 S GRAND AVE 90731
- Application / Permit
- 24016-10000-23069
- Plan Check / Job No.
- B24LA13857
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Soft-Story seismic retrofit per LABC Chapter 93: Install 2- steel special cantilever columns on the west side of the building along the garage door line.
- Permit Issued
- Issued on 3/21/2025
- Issuing Office
- Current Status
- CofC Issued on 5/30/2025
Permit Application Status History
| Submitted | 7/19/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | VARAND SARKISIAN |
| Corrections Issued | 8/5/2024 | VARAND SARKISIAN |
| Quality Review Completed | 8/15/2024 | HANS SANTIAGO |
| Plan Check Approved | 10/15/2024 | VARAND SARKISIAN |
| Issued | 3/21/2025 | APPLICANT |
| OK for CofC | 5/29/2025 | JOEY BUCHANAN |
| OK to Issue CofC | 5/29/2025 | JOEY BUCHANAN |
| CofC Issued | 5/30/2025 | HENRY BAGHDASSARIAN |
Permit Application Clearance Information
| Metro Rail approval | Cleared | 8/27/2024 | JENNIFER SU |
| Eng Process Fee Ord 176,300 | Cleared | 10/2/2024 | ERIK BEASLEY |
| Work Adjacent to Public Way | Cleared | 10/2/2024 | ERIK BEASLEY |
| Tenant Habitability Plan | Cleared | 11/26/2024 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Diego Victor; Lic. No.: 1048380-B | 3267 SANDSTONE CT PALMDALE, CA 93551 |
| Engineer | Dedmari,, Wajahat Hafiz; Lic. No.: NA66819 | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/16/2025 | Approved | JOEY BUCHANAN |
| Excavation/Setback/Form/Re-Bar | 5/1/2025 | Approved | JOEY BUCHANAN |
| Footing/Foundation/Slab | 5/1/2025 | Approved | JOEY BUCHANAN |
| Wood Frame | 5/1/2025 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 5/2/2025 | Conditional Approval | DAVID TSAU |
| Wood Frame | 5/9/2025 | Approved | DARRYL ARNOLD |
| Final | 5/23/2025 | Conditional Approval | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 5/23/2025 | Approved | JOEY BUCHANAN |
| Final | 5/29/2025 | OK for CofC | JOEY BUCHANAN |