2111 1/2 S BRONSON AVE 90018

Certificate Information: 2111 1/2 S BRONSON AVE 90018

Application / Permit
24016-10000-23012
Plan Check / Job No.
B24LA13821
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF THE EXISTING DETACHED GARAGE INTO AN ADU PER STATE LAW
Permit Issued
Issued on 9/5/2024
Issuing Office
Metro
Current Status
CofO Issued on 6/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/18/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 MINA HABILI
Corrections Issued 7/27/2024 MINA HABILI
Building Plans Picked Up 7/31/2024 APPLICANT
Applicant returned to address corrections 8/22/2024 NEHEMIAS RAMOS
Issued 9/5/2024 APPLICANT
CofO in Progress 6/11/2025 JUSTIN HAWLEY
Permit Finaled 6/11/2025 DEROLD HAUFF
CofO Issued 6/11/2025 DEROLD HAUFF
Permit Finaled 6/11/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/1/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 8/1/2024 TREVOR QUAN
Roof/Waste drainage to street Cleared 8/1/2024 TREVOR QUAN
Sewer availability Cleared 8/1/2024 TREVOR QUAN
Tenant Habitability Plan Cleared 8/1/2024 HUGO GARRIDO GARZA
Community Plan Implem. Overlay Cleared 8/21/2024 ISAIAH ROSS

Contact Information

Contractor Owner-Builder       ,
Engineer Richards,, Mark Lee; Lic. No.: C55146 23332 HAWTHORNE BLVD., SUITE 306      TORRANCE, CA 90505

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/6/2024 Corrections Issued JOHN QUINTANILLA
PLUMBING-Rough 11/6/2024 Corrections Issued JOHN QUINTANILLA
Footing/Foundation/Slab 11/7/2024 Partial Approval BRENDAN MORELLI
PLUMBING-Rough 11/8/2024 Approved JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Partial Approval JUSTIN HAWLEY
Footing/Foundation/Slab 11/25/2024 Approved JUSTIN HAWLEY
Sewer 1/3/2025 Approved JUSTIN HAWLEY
BUILDING-Rough-Frame 1/13/2025 Approved JUSTIN HAWLEY
ELECTRICAL-Rough 1/13/2025 Approved JUSTIN HAWLEY
Green Building Rough 1/13/2025 Approved JUSTIN HAWLEY
HVAC-Rough 1/13/2025 Approved JUSTIN HAWLEY
Interior/Exterior Lathing 1/13/2025 Partial Approval JUSTIN HAWLEY
Rough-Elec/Plmb/HVAC 1/13/2025 Approved JUSTIN HAWLEY
Insulation 1/15/2025 Approved ALEX COLIN
Drywall Nailing 1/22/2025 Approved ALEX COLIN
Interior/Exterior Lathing 1/22/2025 Approved ALEX COLIN
Shower Pan 1/22/2025 Approved ALEX COLIN
Final 6/6/2025 Corrections Issued JUSTIN HAWLEY
Green Building Final 6/6/2025 Not Ready for Inspection JUSTIN HAWLEY
SGSOV-Seismic Gas S/O Valve 6/6/2025 SGSOV Not Required JUSTIN HAWLEY
Smoke Detectors 6/6/2025 Approved JUSTIN HAWLEY
Final 6/12/2025 OK to Issue CofO JUSTIN HAWLEY
Green Building Final 6/12/2025 Approved JUSTIN HAWLEY