4338 W 60TH ST 90043
Certificate Information: 4338 W 60TH ST 90043
- Application / Permit
- 24016-10000-22980
- Plan Check / Job No.
- B24LA13811
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- [ePlan] convert 360 ft detached garage into an Accessory Dwelling Unit (ADU)
- Permit Issued
- Issued on 8/9/2024
- Issuing Office
- Current Status
- CofO Issued on 2/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/25/2024 | JOSEPH RAFOLS |
| Corrections Issued | 7/25/2024 | JOSEPH RAFOLS |
| Plan Check Approved | 8/8/2024 | JOSEPH RAFOLS |
| Issued | 8/9/2024 | APPLICANT |
| CofO in Progress | 1/31/2025 | NICHOLAS LOPEZ |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
| CofO Issued | 2/14/2025 | DEROLD HAUFF |
| Permit Finaled | 2/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/27/2024 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 7/27/2024 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/29/2024 | JOSE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 8/7/2024 | CHARLES POWELL |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | L E A D Enterprises Inc; Lic. No.: 955824-B | , |
| Contractor | Pearl Remodeling; Lic. No.: 955824-B | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/26/2024 | Conditional Approval | JOSE MACIAS |
| Footing/Foundation/Slab | 8/30/2024 | Approved | JOSE MACIAS |
| PLUMBING-Rough | 9/23/2024 | Partial Approval | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 10/15/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| ELECTRICAL-Rough | 10/15/2024 | Corrections Issued | AMIR NAZARIAN |
| HVAC-Rough | 10/15/2024 | Approved | AMIR NAZARIAN |
| METHANE-Rough | 10/15/2024 | Approved | AMIR NAZARIAN |
| PLUMBING-Rough | 10/15/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 10/21/2024 | Approved | AMIR NAZARIAN |
| ELECTRICAL-Rough | 10/21/2024 | Conditional Approval | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Partial Approval | AMIR NAZARIAN |
| Insulation | 10/21/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Insulation | 10/24/2024 | Conditional Approval | JOSH MEISTER |
| Interior/Exterior Lathing | 10/24/2024 | Partial Approval | JOSH MEISTER |
| Drywall Nailing | 10/29/2024 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 10/29/2024 | Approved | JOSH MEISTER |
| Shower Pan | 10/29/2024 | Approved | JOSH MEISTER |
| ELECTRICAL-Final | 1/22/2025 | Corrections Issued | NICHOLAS LOPEZ |
| Final | 1/22/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 1/22/2025 | Approved | NICHOLAS LOPEZ |
| PLUMBING-Final | 1/22/2025 | Approved | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/22/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Smoke Detectors | 1/22/2025 | Approved | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 1/28/2025 | Approved | NICHOLAS LOPEZ |
| Final | 1/28/2025 | Corrections Issued | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/28/2025 | SGSOV Not Ready | NICHOLAS LOPEZ |
| Final | 1/31/2025 | OK to Issue CofO | NICHOLAS LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 1/31/2025 | SGSOV Approved | NICHOLAS LOPEZ |