4338 W 60TH ST 90043

Certificate Information: 4338 W 60TH ST 90043

Application / Permit
24016-10000-22980
Plan Check / Job No.
B24LA13811
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
[ePlan] convert 360 ft detached garage into an Accessory Dwelling Unit (ADU)
Permit Issued
Issued on 8/9/2024
Issuing Office
Current Status
CofO Issued on 2/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/23/2024 APPLICANT
Assigned to Plan Check Engineer 7/25/2024 JOSEPH RAFOLS
Corrections Issued 7/25/2024 JOSEPH RAFOLS
Plan Check Approved 8/8/2024 JOSEPH RAFOLS
Issued 8/9/2024 APPLICANT
CofO in Progress 1/31/2025 NICHOLAS LOPEZ
Permit Finaled 2/14/2025 DEROLD HAUFF
CofO Issued 2/14/2025 DEROLD HAUFF
Permit Finaled 2/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/27/2024 JOSE HERNANDEZ
Sewer availability Cleared 7/27/2024 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 7/29/2024 JOSE HERNANDEZ
Grading Pre-Inspection Cleared 8/7/2024 CHARLES POWELL

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor L E A D Enterprises Inc; Lic. No.: 955824-B       ,
Contractor Pearl Remodeling; Lic. No.: 955824-B       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/26/2024 Conditional Approval JOSE MACIAS
Footing/Foundation/Slab 8/30/2024 Approved JOSE MACIAS
PLUMBING-Rough 9/23/2024 Partial Approval AMIR NAZARIAN
BUILDING-Rough-Frame 10/15/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 10/15/2024 Corrections Issued AMIR NAZARIAN
HVAC-Rough 10/15/2024 Approved AMIR NAZARIAN
METHANE-Rough 10/15/2024 Approved AMIR NAZARIAN
PLUMBING-Rough 10/15/2024 Approved AMIR NAZARIAN
BUILDING-Rough-Frame 10/21/2024 Approved AMIR NAZARIAN
ELECTRICAL-Rough 10/21/2024 Conditional Approval AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 10/21/2024 Partial Approval AMIR NAZARIAN
Insulation 10/21/2024 Not Ready for Inspection AMIR NAZARIAN
Insulation 10/24/2024 Conditional Approval JOSH MEISTER
Interior/Exterior Lathing 10/24/2024 Partial Approval JOSH MEISTER
Drywall Nailing 10/29/2024 Approved JOSH MEISTER
Interior/Exterior Lathing 10/29/2024 Approved JOSH MEISTER
Shower Pan 10/29/2024 Approved JOSH MEISTER
ELECTRICAL-Final 1/22/2025 Corrections Issued NICHOLAS LOPEZ
Final 1/22/2025 Corrections Issued NICHOLAS LOPEZ
HVAC-Final 1/22/2025 Approved NICHOLAS LOPEZ
PLUMBING-Final 1/22/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 1/22/2025 SGSOV Not Ready NICHOLAS LOPEZ
Smoke Detectors 1/22/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 1/28/2025 Approved NICHOLAS LOPEZ
Final 1/28/2025 Corrections Issued NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 1/28/2025 SGSOV Not Ready NICHOLAS LOPEZ
Final 1/31/2025 OK to Issue CofO NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 1/31/2025 SGSOV Approved NICHOLAS LOPEZ