356 W MT WASHINGTON DR 90065
Certificate Information: 356 W MT WASHINGTON DR 90065
- Application / Permit
- 24016-10000-22831
- Plan Check / Job No.
- B24LA13693
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel and exterior alteration to (E) SFD w/ attahced deck over carport. (Sister (E) roof framing, re-roof w/ asphalt shingle, replace exterior deck covering and guardrails, replace doors) "COMPLY WITH DEPARTMENT ORDER effective date 08/22/2018. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE" CEIS Case Number is 824892.
- Permit Issued
- Issued on 12/27/2024
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 1/20/2026
Permit Application Status History
| Submitted | 7/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 8/1/2024 | HUAN LE |
| Corrections Issued | 8/29/2024 | HUAN LE |
| Quality Review Completed | 8/30/2024 | KEN GILL |
| Building Plans Picked Up | 9/3/2024 | APPLICANT |
| No Progress | 10/25/2024 | HUAN LE |
| Plan Check Approved | 10/25/2024 | HUAN LE |
| Issued | 12/27/2024 | APPLICANT |
| Permit Finaled | 1/12/2026 | JACOB SEGURA |
Permit Application Clearance Information
| Specific Plan | Cleared | 9/25/2024 | ANDREA MAGANA-WITHERS |
| Miscellaneous | Cleared | 9/26/2024 | DAVID URITA |
| Roof/Waste drainage to street | Cleared | 10/2/2024 | WALLIE JONG |
| Sewer availability | Cleared | 10/2/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 10/3/2024 | WALLIE JONG |
| HPOZ | Cleared | 10/8/2024 | NATHALY DE LA PAZ |
| GPI Written Notices | Cleared | 10/25/2024 | HUAN LE |
| Grading Pre-Inspection | Cleared | 10/25/2024 | RUSSELL BONVOULOIR |
Contact Information
| Architect | Kealani, Grace Jensen; Lic. No.: C39901 | 3572 SHURTLEFF CT LOS ANGELES, CA 90065 |
| Contractor | Axmis Construction; Lic. No.: 1057810-B | 4055 ROSECRANS AVE APT 8 HAWTHORNE, CA 90250 |
| Engineer | Phillips,, Craig; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/4/2025 | No Access for Inspection | JACOB SEGURA |
| Excavation/Setback/Form/Re-Bar | 2/5/2025 | Approved | JACOB SEGURA |
| Footing/Foundation/Slab | 2/5/2025 | Approved | JACOB SEGURA |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2025 | Corrections Issued | JACOB SEGURA |
| BUILDING-Rough-Frame | 3/26/2025 | Corrections Issued | FERMIN RUBIO |
| ELECTRICAL-Rough | 3/26/2025 | Corrections Issued | FERMIN RUBIO |
| HVAC-Rough | 3/26/2025 | Corrections Issued | FERMIN RUBIO |
| PLUMBING-Rough | 3/26/2025 | Corrections Issued | FERMIN RUBIO |
| BUILDING-Rough-Frame | 4/1/2025 | Corrections Issued | JACOB SEGURA |
| ELECTRICAL-Rough | 4/1/2025 | Corrections Issued | JACOB SEGURA |
| HVAC-Rough | 4/1/2025 | Partial Approval | JACOB SEGURA |
| PLUMBING-Rough | 4/1/2025 | Partial Approval | JACOB SEGURA |
| BUILDING-Rough-Frame | 4/8/2025 | Corrections Issued | JACOB SEGURA |
| ELECTRICAL-Rough | 4/8/2025 | Partial Approval | JACOB SEGURA |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Partial Approval | JACOB SEGURA |
| HVAC-Rough | 4/8/2025 | Partial Approval | JACOB SEGURA |
| PLUMBING-Rough | 4/8/2025 | Approved | JACOB SEGURA |
| Wood Frame | 4/10/2025 | No Access for Inspection | JACOB SEGURA |
| Insulation | 4/15/2025 | Partial Approval | JACOB SEGURA |
| Deputy Wood Construction | 4/18/2025 | No Access for Inspection | JACOB SEGURA |
| BUILDING-Rough-Frame | 4/29/2025 | Partial Approval | JACOB SEGURA |
| Deputy Wood Construction | 4/29/2025 | Corrections Issued | JACOB SEGURA |
| Floor/Roof Diaphrgm/Shear Wall | 4/29/2025 | Partial Approval | JACOB SEGURA |
| Interior/Exterior Lathing | 4/29/2025 | Approved | JACOB SEGURA |
| BUILDING-Rough-Frame | 5/6/2025 | Approved | JACOB SEGURA |
| ELECTRICAL-Rough | 5/6/2025 | Approved | JACOB SEGURA |
| Wood Frame | 5/6/2025 | Approved | JACOB SEGURA |
| Drywall Nailing | 5/16/2025 | Partial Approval | JACOB SEGURA |
| Drywall Nailing | 6/10/2025 | Approved | JACOB SEGURA |
| HVAC-Rough | 6/10/2025 | Corrections Issued | JACOB SEGURA |
| Wood Frame | 6/10/2025 | Approved | JACOB SEGURA |
| Interior/Exterior Lathing | 9/15/2025 | Approved | JACOB SEGURA |
| ELECTRICAL-Final | 9/24/2025 | Corrections Issued | JACOB SEGURA |
| Final | 9/24/2025 | Corrections Issued | JACOB SEGURA |
| HVAC-Final | 9/24/2025 | Corrections Issued | JACOB SEGURA |
| PLUMBING-Final | 9/24/2025 | Corrections Issued | JACOB SEGURA |
| SGSOV-Seismic Gas S/O Valve | 9/24/2025 | SGSOV Approved | JACOB SEGURA |
| Service/Power Release | 9/24/2025 | Not Ready for Inspection | JACOB SEGURA |
| Smoke Detectors | 9/24/2025 | Approved | JACOB SEGURA |
| ELECTRICAL-Final | 10/9/2025 | Corrections Issued | JACOB SEGURA |
| HVAC-Final | 10/9/2025 | Partial Approval | JACOB SEGURA |
| PLUMBING-Final | 10/9/2025 | Partial Approval | JACOB SEGURA |
| ELECTRICAL-Final | 11/14/2025 | Not Ready for Inspection | JACOB SEGURA |
| Final | 11/14/2025 | Not Ready for Inspection | JACOB SEGURA |
| HVAC-Final | 11/14/2025 | Not Ready for Inspection | JACOB SEGURA |
| PLUMBING-Final | 11/14/2025 | Not Ready for Inspection | JACOB SEGURA |
| ELECTRICAL-Final | 11/19/2025 | Partial Approval | JACOB SEGURA |
| HVAC-Final | 11/19/2025 | Approved | JACOB SEGURA |
| PLUMBING-Final | 11/19/2025 | Partial Approval | JACOB SEGURA |
| ELECTRICAL-Final | 1/5/2026 | No Access for Inspection | JACOB SEGURA |
| Final | 1/5/2026 | No Access for Inspection | JACOB SEGURA |
| HVAC-Final | 1/5/2026 | No Access for Inspection | JACOB SEGURA |
| PLUMBING-Final | 1/5/2026 | No Access for Inspection | JACOB SEGURA |
| ELECTRICAL-Final | 1/12/2026 | Approved | JACOB SEGURA |
| Final | 1/12/2026 | Permit Finaled | JACOB SEGURA |
| HVAC-Final | 1/12/2026 | Approved | JACOB SEGURA |
| PLUMBING-Final | 1/12/2026 | Approved | JACOB SEGURA |