2143 S PONTIUS AVE 90025
Certificate Information: 2143 S PONTIUS AVE 90025
- Application / Permit
- 24016-10000-22768
- Plan Check / Job No.
- B24LA13669
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (8) Automobile Repairing
- Work Description
- T.I. OF (E) AUTO REPAIR FACILITY WITH STRUCTURAL ALTERATIONS FOR NEW ROOFTOP EQUIPMENT AND NEW STOREFRONT. ***SHALL BE SPRINKLERED PER NFPA13***
- Permit Issued
- Issued on 9/18/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 9/4/2025
Permit Application Status History
| Submitted | 7/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2024 | MICHAEL LOPEZ |
| Assigned to Zoning Architect | 7/19/2024 | JASON BRAVO |
| Corrections Issued | 8/1/2024 | MICHAEL LOPEZ |
| Building Plans Picked Up | 8/1/2024 | APPLICANT |
| Quality Review Completed | 8/2/2024 | KEN GILL |
| Applicant returned to address corrections | 9/12/2024 | MICHAEL LOPEZ |
| Plan Check Approved | 9/18/2024 | MICHAEL LOPEZ |
| Issued | 9/18/2024 | APPLICANT |
| Permit Finaled | 9/3/2025 | VASIL MIHALEV |
Permit Application Clearance Information
| Miscellaneous | Cleared | 8/6/2024 | DAVID URITA |
| Miscellaneous | Cleared | 8/6/2024 | DAVID URITA |
| Miscellaneous | Cleared | 8/6/2024 | DAVID URITA |
| Miscellaneous | Cleared | 8/6/2024 | DAVID URITA |
| DAS Clearance | Cleared | 9/4/2024 | MICHAEL LOPEZ |
| Zoning Plan Check | Cleared | 9/11/2024 | MICHAEL LOPEZ |
Contact Information
| Contractor | A B C Advance Builder & Constructor Inc; Lic. No.: 989468-B | 18017 CHATSWORTH STREET #140 GRANADA HILLS, CA 91344 |
| Engineer | Vaziri,, Babak; Lic. No.: S3985 | 905 4TH STREET SAN RAFAEL, CA 94901 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 10/28/2024 | Conditional Approval | MICHAEL PETRUSKO |
| Footing/Foundation/Slab | 10/29/2024 | Partial Approval | FARHAD DADBIN |
| Insulation | 11/14/2024 | Approved | MICHAEL PETRUSKO |
| Deputy Wood Construction | 11/19/2024 | Conditional Approval | MICHAEL PETRUSKO |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Approved | MICHAEL PETRUSKO |
| Insulation | 1/7/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Light Gage Steel Frame | 1/7/2025 | No Access for Inspection | RICARDO ROBLES |
| Insulation | 1/9/2025 | Approved | RICARDO ROBLES |
| Light Gage Steel Frame | 1/9/2025 | Approved | RICARDO ROBLES |
| Drywall Nailing | 1/16/2025 | Approved | FARHAD DADBIN |
| Final | 6/13/2025 | Not Ready for Inspection | VASIL MIHALEV |
| SGSOV-Seismic Gas S/O Valve | 6/13/2025 | SGSOV Not Required | VASIL MIHALEV |
| Smoke Detectors | 6/13/2025 | Approved | VASIL MIHALEV |
| Final | 9/3/2025 | Permit Finaled | VASIL MIHALEV |