Green Building Rough
|
12/13/2024
|
Not Ready for Inspection
|
ALFREDO LOPEZ
|
METHANE-Rough
|
12/13/2024
|
Partial Approval
|
ALFREDO LOPEZ
|
Reinforced Concrete Frame
|
12/13/2024
|
Partial Approval
|
ALFREDO LOPEZ
|
Verify Sprinkler Sign Off
|
12/13/2024
|
Not Ready for Inspection
|
ALFREDO LOPEZ
|
Structural Steel Frame
|
12/16/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
Green Building Rough
|
12/17/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
METHANE-Rough
|
12/17/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
Reinforced Concrete Frame
|
12/17/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
Verify Sprinkler Sign Off
|
12/17/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
Green Building Rough
|
12/18/2024
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
METHANE-Rough
|
12/18/2024
|
Approved
|
RONALD JIMENEZ
|
Reinforced Concrete Frame
|
12/18/2024
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
Verify Sprinkler Sign Off
|
12/18/2024
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
Excavation/Setback/Form/Re-Bar
|
12/19/2024
|
Partial Approval
|
RONALD JIMENEZ
|
Reinforced Concrete Frame
|
12/19/2024
|
Partial Approval
|
RONALD JIMENEZ
|
Footing/Foundation/Slab
|
12/20/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
Green Building Rough
|
12/20/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
METHANE-Barrier
|
12/20/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
METHANE-Subgrade
|
12/20/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
Reinforced Concrete Frame
|
12/20/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
Verify Sprinkler Sign Off
|
12/20/2024
|
Partial Approval
|
JEROME BLACKWOOD
|
Green Building Rough
|
12/21/2024
|
Not Ready for Inspection
|
LUIS CCAMACHO
|
Reinforced Concrete Frame
|
12/21/2024
|
Partial Inspection
|
LUIS CCAMACHO
|
Verify Sprinkler Sign Off
|
12/21/2024
|
Not Ready for Inspection
|
LUIS CCAMACHO
|
Pre-Inspection
|
12/22/2024
|
Partial Approval
|
RAFAEL CORTES
|
Green Building Rough
|
12/23/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
Reinforced Concrete Frame
|
12/23/2024
|
Partial Approval
|
RAMAZANALI ALMASI
|
Verify Sprinkler Sign Off
|
12/23/2024
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
Green Building Rough
|
12/26/2024
|
Not Ready for Inspection
|
TIMOTHY POWELL
|
Green Building Rough
|
12/26/2024
|
Off-Hour Fees Due
|
|
Reinforced Concrete Frame
|
12/26/2024
|
Off-Hour Fees Due
|
|
Reinforced Concrete Frame
|
12/26/2024
|
Partial Approval
|
TIMOTHY POWELL
|
Verify Sprinkler Sign Off
|
12/26/2024
|
Not Ready for Inspection
|
TIMOTHY POWELL
|
Verify Sprinkler Sign Off
|
12/26/2024
|
Off-Hour Fees Due
|
|
Excavation/Setback/Form/Re-Bar
|
12/27/2024
|
Off-Hour Fees Due
|
|
Footing/Foundation/Slab
|
12/27/2024
|
Partial Approval
|
RONALD JIMENEZ
|
METHANE-Barrier
|
12/27/2024
|
Approved
|
RONALD JIMENEZ
|
METHANE-Subgrade
|
12/27/2024
|
Approved
|
RONALD JIMENEZ
|
Pre-Inspection
|
12/27/2024
|
Conditional Approval
|
RAMAZANALI ALMASI
|
Pre-Inspection
|
12/28/2024
|
Off-Hour Fees Due
|
|
Pre-Inspection
|
12/28/2024
|
Partial Approval
|
MARTIN TAVITIAN
|
Pre-Inspection
|
12/30/2024
|
Approved
|
DARRYL ARNOLD
|
Pre-Inspection
|
12/30/2024
|
Off-Hour Fees Due
|
|
Pre-Inspection
|
1/2/2025
|
Off-Hour Fees Due
|
|
Pre-Inspection
|
1/2/2025
|
Partial Approval
|
JEROME BLACKWOOD
|
Drywall Nailing
|
1/3/2025
|
Off-Hour Fees Due
|
|
Drywall Nailing
|
1/3/2025
|
Partial Approval
|
RAFAEL CORTES
|
Green Building Rough
|
1/3/2025
|
Approved
|
RONALD JIMENEZ
|
Light Gage Steel Frame
|
1/3/2025
|
Off-Hour Fees Due
|
|
Light Gage Steel Frame
|
1/3/2025
|
Partial Approval
|
RAFAEL CORTES
|
Reinforced Concrete Frame
|
1/3/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Verify Sprinkler Sign Off
|
1/3/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
Insulation
|
1/8/2025
|
Approved
|
RONALD JIMENEZ
|
Pre-Inspection
|
1/8/2025
|
Approved
|
RONALD JIMENEZ
|
Drywall Nailing
|
1/9/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Insulation
|
1/9/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
Deputy Reinf. Concrete
|
1/10/2025
|
Conditional Approval
|
RAMAZANALI ALMASI
|
Drywall Nailing
|
1/10/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Footing/Foundation/Slab
|
1/10/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
Excavation/Setback/Form/Re-Bar
|
1/11/2025
|
Approved
|
DARRYL ARNOLD
|
Drywall Nailing
|
1/13/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Insulation
|
1/13/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Light Gage Steel Frame
|
1/13/2025
|
Approved
|
RONALD JIMENEZ
|
Excavation/Setback/Form/Re-Bar
|
1/14/2025
|
Partial Approval
|
JEROME BLACKWOOD
|
Footing/Foundation/Slab
|
1/14/2025
|
Partial Approval
|
JEROME BLACKWOOD
|
Reinforced Concrete Frame
|
1/14/2025
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
Verify Sprinkler Sign Off
|
1/14/2025
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
Drywall Nailing
|
1/15/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Footing/Foundation/Slab
|
1/15/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Insulation
|
1/15/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Excavation/Setback/Form/Re-Bar
|
1/16/2025
|
Partial Approval
|
LUIS CCAMACHO
|
Footing/Foundation/Slab
|
1/16/2025
|
Partial Approval
|
LUIS CCAMACHO
|
Reinforced Concrete Frame
|
1/16/2025
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
Verify Sprinkler Sign Off
|
1/16/2025
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
Drywall Nailing
|
1/17/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Floor/Roof Diaphrgm/Shear Wall
|
1/17/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Excavation/Setback/Form/Re-Bar
|
1/18/2025
|
Off-Hour Fees Due
|
|
Excavation/Setback/Form/Re-Bar
|
1/20/2025
|
Partial Approval
|
JAMES POWERS
|
Excavation/Setback/Form/Re-Bar
|
1/22/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Footing/Foundation/Slab
|
1/22/2025
|
Partial Approval
|
ALFREDO LOPEZ
|
Pre-Inspection
|
1/22/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Reinforced Concrete Frame
|
1/22/2025
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
Verify Sprinkler Sign Off
|
1/22/2025
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
Excavation/Setback/Form/Re-Bar
|
1/23/2025
|
Off-Hour Fees Due
|
|
Reinforced Concrete Frame
|
1/23/2025
|
Not Ready for Inspection
|
DARRYL ARNOLD
|
Drywall Nailing
|
1/24/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Excavation/Setback/Form/Re-Bar
|
1/24/2025
|
Partial Approval
|
LUIS CCAMACHO
|
Excavation/Setback/Form/Re-Bar
|
1/24/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Footing/Foundation/Slab
|
1/24/2025
|
Partial Approval
|
RONALD JIMENEZ
|
T-Bar Ceiling
|
1/24/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
Drywall Nailing
|
1/25/2025
|
Conditional Approval
|
DARRYL ARNOLD
|
Excavation/Setback/Form/Re-Bar
|
1/25/2025
|
Partial Approval
|
ALFREDO LOPEZ
|
Light Gage Steel Frame
|
1/25/2025
|
Conditional Approval
|
DARRYL ARNOLD
|
T-Bar Ceiling
|
1/25/2025
|
Conditional Approval
|
DARRYL ARNOLD
|
Excavation/Setback/Form/Re-Bar
|
1/27/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Drywall Nailing
|
1/28/2025
|
Approved
|
DARRYL ARNOLD
|
Excavation/Setback/Form/Re-Bar
|
1/28/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Light Gage Steel Frame
|
1/28/2025
|
Approved
|
DARRYL ARNOLD
|
Excavation/Setback/Form/Re-Bar
|
1/29/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
Reinforced Masonry Frame
|
1/30/2025
|
Approved
|
RONALD JIMENEZ
|
Excavation/Setback/Form/Re-Bar
|
1/31/2025
|
Approved
|
RONALD JIMENEZ
|
Excavation/Setback/Form/Re-Bar
|
1/31/2025
|
Partial Approval
|
LUIS CCAMACHO
|
Excavation/Setback/Form/Re-Bar
|
2/1/2025
|
Off-Hour Fees Due
|
|
Light Gage Steel Frame
|
2/1/2025
|
Approved
|
DARRYL ARNOLD
|
Excavation/Setback/Form/Re-Bar
|
2/2/2025
|
Approved
|
DARRYL ARNOLD
|
Excavation/Setback/Form/Re-Bar
|
2/3/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Reinforced Concrete Frame
|
2/3/2025
|
Not Ready for Inspection
|
CHRISTOPHER BLACKWOOD
|
Excavation/Setback/Form/Re-Bar
|
2/5/2025
|
Partial Approval
|
ALFREDO LOPEZ
|
Excavation/Setback/Form/Re-Bar
|
2/6/2025
|
Partial Approval
|
TIMOTHY POWELL
|
Light Gage Steel Frame
|
2/6/2025
|
Partial Approval
|
TIMOTHY POWELL
|
Excavation/Setback/Form/Re-Bar
|
2/7/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Light Gage Steel Frame
|
2/7/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Reinforced Concrete Frame
|
2/7/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Excavation/Setback/Form/Re-Bar
|
2/8/2025
|
Conditional Approval
|
DARRYL ARNOLD
|
Excavation/Setback/Form/Re-Bar
|
2/10/2025
|
Partial Approval
|
PAUL BAZERKANIAN
|
Excavation/Setback/Form/Re-Bar
|
2/11/2025
|
Off-Hour Fees Due
|
|
Excavation/Setback/Form/Re-Bar
|
2/11/2025
|
Partial Approval
|
CHRISTOPHER BLACKWOOD
|
Light Gage Steel Frame
|
2/12/2025
|
Partial Approval
|
RAFAEL CORTES
|
Light Gage Steel Frame
|
2/13/2025
|
Partial Approval
|
ALFREDO LOPEZ
|
Light Gage Steel Frame
|
2/13/2025
|
Partial Approval
|
JEROME BLACKWOOD
|
Drywall Nailing
|
2/14/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Excavation/Setback/Form/Re-Bar
|
2/14/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Light Gage Steel Frame
|
2/14/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Light Gage Steel Frame
|
2/15/2025
|
Partial Approval
|
MARTIN TAVITIAN
|
Excavation/Setback/Form/Re-Bar
|
2/16/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Excavation/Setback/Form/Re-Bar
|
2/17/2025
|
Conditional Approval
|
DARRYL ARNOLD
|
Excavation/Setback/Form/Re-Bar
|
2/18/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Footing/Foundation/Slab
|
2/18/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Deputy Reinf. Concrete
|
2/20/2025
|
Conditional Approval
|
RAMAZANALI ALMASI
|
Excavation/Setback/Form/Re-Bar
|
2/20/2025
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
Excavation/Setback/Form/Re-Bar
|
2/20/2025
|
Off-Hour Fees Due
|
|
Excavation/Setback/Form/Re-Bar
|
2/20/2025
|
Partial Approval
|
CHRISTOPHER BLACKWOOD
|
Light Gage Steel Frame
|
2/20/2025
|
Not Ready for Inspection
|
RAMAZANALI ALMASI
|
Deputy Reinf. Concrete
|
2/21/2025
|
Conditional Approval
|
RONALD JIMENEZ
|
Excavation/Setback/Form/Re-Bar
|
2/21/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Light Gage Steel Frame
|
2/21/2025
|
Partial Approval
|
LUIS CCAMACHO
|
T-Bar Ceiling
|
2/22/2025
|
Partial Approval
|
RAFAEL CORTES
|
T-Bar Ceiling
|
2/25/2025
|
Partial Approval
|
ALFREDO LOPEZ
|
Light Gage Steel Frame
|
2/26/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
T-Bar Ceiling
|
2/26/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Excavation/Setback/Form/Re-Bar
|
2/27/2025
|
Partial Approval
|
JEROME BLACKWOOD
|
Light Gage Steel Frame
|
2/27/2025
|
Partial Approval
|
JEROME BLACKWOOD
|
Drywall Nailing
|
2/28/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Light Gage Steel Frame
|
2/28/2025
|
Partial Approval
|
RAMAZANALI ALMASI
|
Special/Order Compliance
|
3/1/2025
|
Approved
|
RONALD JIMENEZ
|
Excavation/Setback/Form/Re-Bar
|
3/10/2025
|
Approved
|
RONALD JIMENEZ
|
Final
|
3/11/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
Footing/Foundation/Slab
|
3/11/2025
|
Approved
|
RONALD JIMENEZ
|
Green Building Final
|
3/11/2025
|
Approved
|
RONALD JIMENEZ
|
Reinforced Concrete Frame
|
3/11/2025
|
Partial Approval
|
RONALD JIMENEZ
|
SGSOV-Seismic Gas S/O Valve
|
3/11/2025
|
SGSOV Approved
|
RONALD JIMENEZ
|
Smoke Detectors
|
3/11/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
Verify Sprinkler Sign Off
|
3/11/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
Drywall Nailing
|
3/13/2025
|
Approved
|
RONALD JIMENEZ
|
Light Gage Steel Frame
|
3/13/2025
|
Approved
|
RONALD JIMENEZ
|
Pre-Inspection
|
3/13/2025
|
Approved
|
RONALD JIMENEZ
|
Final
|
3/17/2025
|
Partial Inspection
|
RONALD JIMENEZ
|
Reinforced Concrete Frame
|
3/17/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Smoke Detectors
|
3/17/2025
|
Approved
|
RONALD JIMENEZ
|
Verify Sprinkler Sign Off
|
3/17/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
Final
|
4/25/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
Reinforced Concrete Frame
|
4/25/2025
|
Partial Approval
|
RONALD JIMENEZ
|
Verify Sprinkler Sign Off
|
4/25/2025
|
Not Ready for Inspection
|
RONALD JIMENEZ
|
Final
|
5/1/2025
|
OK to Issue CofO
|
RONALD JIMENEZ
|
Reinforced Concrete Frame
|
5/1/2025
|
Approved
|
RONALD JIMENEZ
|
Verify Sprinkler Sign Off
|
5/1/2025
|
Approved
|
RONALD JIMENEZ
|