7960 W FAREHOLM DR 90046

Certificate Information: 7960 W FAREHOLM DR 90046

Application / Permit
24016-10000-22715
Plan Check / Job No.
B24LA13633
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: Supplemental to 20016-10000-02638 to revise the recreation room layout and structual plans.
Permit Issued
Issued on 10/7/2024
Issuing Office
Current Status
Permit Finaled on 4/10/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/16/2024 APPLICANT
Assigned to Plan Check Engineer 7/18/2024 HELEN NGUYEN
Corrections Issued 7/22/2024 HELEN NGUYEN
Quality Review Completed 7/23/2024 PETER KIM
Applicant returned to address corrections 8/21/2024 HELEN NGUYEN
Applicant returned to address corrections 8/29/2024 HELEN NGUYEN
Applicant returned to address corrections 9/16/2024 HELEN NGUYEN
Applicant returned to address corrections 9/20/2024 HELEN NGUYEN
Plan Check Approved 10/4/2024 HELEN NGUYEN
Issued 10/7/2024 APPLICANT
Permit Finaled 4/9/2026 ROY SPAULDING

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Shichishima,, Kazushige; Lic. No.: C34034 742 N BROADWAY SUITE 201      LOS ANGELES, CA 90012
Contractor Taconic Builders Inc; Lic. No.: 930731-B       ,
Engineer Paulino,, Juan Manuel; Lic. No.: C87963 636 N TERRACE AVE 3H      MOUNT VERNON, NY 10552

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/4/2024 Partial Inspection BRIAN SULLIVAN
Piling/Pier/Caisson 11/4/2024 Partial Inspection BRIAN SULLIVAN
Pre-Inspection 11/4/2024 Partial Inspection BRIAN SULLIVAN
Excavation/Setback/Form/Re-Bar 11/8/2024 Partial Approval RAUL BARAJAS
Piling/Pier/Caisson 11/8/2024 Partial Approval RAUL BARAJAS
Pre-Inspection 11/8/2024 Corrections Issued RAUL BARAJAS
Piling/Pier/Caisson 3/24/2025 Partial Approval ROY SPAULDING
Reinforced Concrete Frame 3/24/2025 Partial Approval ROY SPAULDING
Structural Steel Frame 3/24/2025 Partial Approval ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Approved ROY SPAULDING
Wood Frame 4/23/2025 Partial Approval ROY SPAULDING
Pre-Inspection 10/1/2025 Not Ready for Inspection ROY SPAULDING
Wood Frame 10/15/2025 Partial Approval ROY SPAULDING
Floor/Roof Diaphrgm/Shear Wall 10/30/2025 Approved ROY SPAULDING
Light Gage Steel Frame 10/30/2025 Not Ready for Inspection ROY SPAULDING
Wood Frame 10/30/2025 Not Ready for Inspection ROY SPAULDING
Interior/Exterior Lathing 11/19/2025 Approved ROY SPAULDING
Insulation 11/21/2025 Approved ROY SPAULDING
Drywall Nailing 12/11/2025 Approved DAVID WILLIAMS
SGSOV-Seismic Gas S/O Valve 2/9/2026 SGSOV Not Ready ROY SPAULDING
Final 3/19/2026 Corrections Issued ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 3/19/2026 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 3/19/2026 Not Ready for Inspection ROY SPAULDING
Wood Frame 3/19/2026 Approved ROY SPAULDING
Final 4/9/2026 Permit Finaled ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 4/9/2026 SGSOV Approved ROY SPAULDING
Smoke Detectors 4/9/2026 Approved ROY SPAULDING