1059 W 81ST ST 90044
Certificate Information: 1059 W 81ST ST 90044
- Application / Permit
- 24016-10000-22597
- Plan Check / Job No.
- B24LA13553
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: CONVERT (E) DETACHED GARAGE INTO (N) 329 SF ADU PER GCS 65852.2(e)(1)(A). ALL WORK PER ENG.
- Permit Issued
- Issued on 1/2/2025
- Issuing Office
- Current Status
- CofO Issued on 1/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/22/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 7/23/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 12/20/2024 | SERGIO MUNIZ |
| Applicant returned to address corrections | 12/27/2024 | SERGIO MUNIZ |
| Plan Check Approved | 1/1/2025 | ARAMIK SHAHMIRZAIAN |
| Issued | 1/2/2025 | APPLICANT |
| CofO in Progress | 1/6/2026 | JOHN QUINTANILLA |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
| Permit Finaled | 1/9/2026 | DEROLD HAUFF |
| CofO Issued | 1/9/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 8/20/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 8/20/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/21/2024 | DAVID LOPEZ |
| Construction near power lines | Cleared | 11/13/2024 | RIDWAN HARDY |
| ZI | Cleared | 12/5/2024 | MANERI ROMAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/16/2025 | Corrections Issued | JOHN QUINTANILLA |
| Pre-Inspection | 5/16/2025 | Partial Inspection | JOHN QUINTANILLA |
| Excavation/Setback/Form/Re-Bar | 6/18/2025 | Corrections Issued | JOHN QUINTANILLA |
| Underground Mechanical | 6/18/2025 | Approved | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 6/23/2025 | Corrections Issued | LUIS CASTRO |
| Deputy Drilled-In Anchors | 6/26/2025 | Conditional Approval | ANTHONY RAMOS |
| ELECTRICAL-Rough | 7/24/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 7/24/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 8/25/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 8/25/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Sewer | 8/25/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 9/5/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| PLUMBING-Rough | 9/5/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 9/8/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| HVAC-Rough | 9/8/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 9/10/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 9/10/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 9/11/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 9/11/2025 | Approved | JOHN QUINTANILLA |
| Wood Frame | 9/11/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2025 | Partial Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 9/30/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 9/30/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 10/2/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 10/6/2025 | Approved | JOSH MEISTER |
| Shower Pan | 10/8/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 10/9/2025 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 10/22/2025 | Corrections Issued | JOHN QUINTANILLA |
| HVAC-Final | 11/3/2025 | Corrections Issued | BARRY HACHE |
| PLUMBING-Final | 11/3/2025 | Corrections Issued | BARRY HACHE |
| ELECTRICAL-Final | 11/5/2025 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Final | 11/5/2025 | Approved | JOHN QUINTANILLA |
| Final | 11/6/2025 | Conditional Approval | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 11/6/2025 | SGSOV Not Required | JOHN QUINTANILLA |
| Service/Power Release | 11/6/2025 | Approved | JOHN QUINTANILLA |
| Smoke Detectors | 11/6/2025 | Approved | JOHN QUINTANILLA |
| Final | 12/24/2025 | Conditional Approval | JOHN QUINTANILLA |
| Final | 1/5/2026 | OK to Issue CofO | JOHN QUINTANILLA |