1059 W 81ST ST 90044

Certificate Information: 1059 W 81ST ST 90044

Application / Permit
24016-10000-22597
Plan Check / Job No.
B24LA13553
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: CONVERT (E) DETACHED GARAGE INTO (N) 329 SF ADU PER GCS 65852.2(e)(1)(A). ALL WORK PER ENG.
Permit Issued
Issued on 1/2/2025
Issuing Office
Current Status
CofO Issued on 1/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/17/2024 APPLICANT
Assigned to Plan Check Engineer 7/22/2024 LUISANGEL VALENZUELA
Corrections Issued 7/23/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 12/20/2024 SERGIO MUNIZ
Applicant returned to address corrections 12/27/2024 SERGIO MUNIZ
Plan Check Approved 1/1/2025 ARAMIK SHAHMIRZAIAN
Issued 1/2/2025 APPLICANT
CofO in Progress 1/6/2026 JOHN QUINTANILLA
Permit Finaled 1/9/2026 DEROLD HAUFF
Permit Finaled 1/9/2026 DEROLD HAUFF
CofO Issued 1/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 8/20/2024 DAVID LOPEZ
Sewer availability Cleared 8/20/2024 DAVID LOPEZ
Eng Process Fee Ord 176,300 Cleared 8/21/2024 DAVID LOPEZ
Construction near power lines Cleared 11/13/2024 RIDWAN HARDY
ZI Cleared 12/5/2024 MANERI ROMAN

Contact Information

Contractor Owner-Builder       ,
Engineer Ramirez, Cid, Jose Carlos; Lic. No.: C91046 5164 N RATON CIR      LONG BEACH, CA 90807

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/16/2025 Corrections Issued JOHN QUINTANILLA
Pre-Inspection 5/16/2025 Partial Inspection JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 6/18/2025 Corrections Issued JOHN QUINTANILLA
Underground Mechanical 6/18/2025 Approved JOHN QUINTANILLA
Footing/Foundation/Slab 6/23/2025 Corrections Issued LUIS CASTRO
Deputy Drilled-In Anchors 6/26/2025 Conditional Approval ANTHONY RAMOS
ELECTRICAL-Rough 7/24/2025 Not Ready for Inspection JOHN QUINTANILLA
Footing/Foundation/Slab 7/24/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 8/25/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 8/25/2025 Corrections Issued SALVADOR MARTINEZ
Sewer 8/25/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Rough 9/5/2025 Not Ready for Inspection JOHN QUINTANILLA
PLUMBING-Rough 9/5/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 9/8/2025 Not Ready for Inspection JOHN QUINTANILLA
HVAC-Rough 9/8/2025 Not Ready for Inspection JOHN QUINTANILLA
ELECTRICAL-Rough 9/10/2025 Approved JOHN QUINTANILLA
HVAC-Rough 9/10/2025 Approved JOHN QUINTANILLA
ELECTRICAL-Rough 9/11/2025 Approved JOHN QUINTANILLA
HVAC-Rough 9/11/2025 Approved JOHN QUINTANILLA
Wood Frame 9/11/2025 Not Ready for Inspection JOHN QUINTANILLA
Floor/Roof Diaphrgm/Shear Wall 9/26/2025 Partial Approval SALVADOR MARTINEZ
BUILDING-Rough-Frame 9/30/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 9/30/2025 Approved JOHN QUINTANILLA
Insulation 10/2/2025 Approved JOHN QUINTANILLA
Drywall Nailing 10/6/2025 Approved JOSH MEISTER
Shower Pan 10/8/2025 Approved JOHN QUINTANILLA
Interior/Exterior Lathing 10/9/2025 Approved JOHN QUINTANILLA
Service/Power Release 10/22/2025 Corrections Issued JOHN QUINTANILLA
HVAC-Final 11/3/2025 Corrections Issued BARRY HACHE
PLUMBING-Final 11/3/2025 Corrections Issued BARRY HACHE
ELECTRICAL-Final 11/5/2025 Corrections Issued JOHN QUINTANILLA
PLUMBING-Final 11/5/2025 Approved JOHN QUINTANILLA
Final 11/6/2025 Conditional Approval JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 11/6/2025 SGSOV Not Required JOHN QUINTANILLA
Service/Power Release 11/6/2025 Approved JOHN QUINTANILLA
Smoke Detectors 11/6/2025 Approved JOHN QUINTANILLA
Final 12/24/2025 Conditional Approval JOHN QUINTANILLA
Final 1/5/2026 OK to Issue CofO JOHN QUINTANILLA