228 N SOTO ST 90033
Certificate Information: 228 N SOTO ST 90033
- Application / Permit
- 24016-10000-22472
- Plan Check / Job No.
- B24LA13471
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (23) Miscellaneous Bldg/Structure
- Work Description
- ePLAN. NEW DETACHED TRASH ENCLOSURE PER WFPP.
- Permit Issued
- Issued on 8/9/2024
- Issuing Office
- Current Status
- CofO Issued on 11/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2024 | KEVIN MORALES |
| Corrections Issued | 7/25/2024 | KEVIN MORALES |
| Quality Review Completed | 7/29/2024 | EUGENE BARBEAU |
| Applicant returned to address corrections | 7/31/2024 | KEVIN MORALES |
| Plan Check Approved | 8/8/2024 | KEVIN MORALES |
| Issued | 8/9/2024 | APPLICANT |
| CofO in Progress | 11/17/2025 | RAFAEL CORTES |
| Permit Finaled | 11/18/2025 | ERNESTO CORRAL |
| Permit Finaled | 11/18/2025 | ERNESTO CORRAL |
| CofO Issued | 11/18/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 7/29/2024 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 7/29/2024 | YASMINE BASHIRI |
| Roof/Waste drainage to street | Cleared | 7/30/2024 | WALLIE JONG |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2024 | WALLIE JONG |
| Metro Rail approval | Cleared | 8/5/2024 | JENNIFER SU |
Contact Information
| Contractor | Mid Construction Group; Lic. No.: 1030925-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/8/2025 | Approved | RONALD JIMENEZ |
| Excavation/Setback/Form/Re-Bar | 4/18/2025 | Not Ready for Inspection | LARRY ARNICK |
| Deputy Drilled-In Anchors | 4/21/2025 | Conditional Approval | LARRY ARNICK |
| Excavation/Setback/Form/Re-Bar | 4/21/2025 | Partial Approval | LARRY ARNICK |
| Final | 9/18/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 9/18/2025 | Not Ready for Inspection | RAFAEL CORTES |
| METHANE-Barrier | 9/18/2025 | Approved | RAFAEL CORTES |
| METHANE-Final | 9/18/2025 | Approved | RAFAEL CORTES |
| METHANE-Rough | 9/18/2025 | Approved | RAFAEL CORTES |
| METHANE-Subgrade | 9/18/2025 | Approved | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 9/18/2025 | SGSOV Approved | RAFAEL CORTES |
| Smoke Detectors | 9/18/2025 | Approved | RAFAEL CORTES |
| Verify Sprinkler Sign Off | 9/18/2025 | Approved | RAFAEL CORTES |
| Wood Frame | 9/18/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 9/26/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 9/26/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 9/26/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 10/14/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Footing/Foundation/Slab | 10/14/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Wood Frame | 10/14/2025 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 11/17/2025 | OK to Issue CofO | RAFAEL CORTES |
| Footing/Foundation/Slab | 11/17/2025 | Approved | RAFAEL CORTES |
| Wood Frame | 11/17/2025 | Approved | RAFAEL CORTES |