1332 S HARBOR BLVD 90731
Certificate Information: 1332 S HARBOR BLVD 90731
- Application / Permit
- 24016-10000-22192
- Plan Check / Job No.
- B24LA13263
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- TENANT IMPROVEMENT OF THE NEW HOPSCOTCH SHOWROOM IN WEST HARBOR. SCOPE LIMITED TO NEW RESTROOMS, PRIVATE LOUNGE & WAITING AREA WITH ADJACENT BAR PREP AREA. ALL NEW WORK WITHIN AN EXISTING CORE AND SHELL BUILDING PERMITTED UNDER PA # 19010-10000-01499 AND ALL RELATED SUPPLEMENTS. NO EXTERIOR WORK.
- Permit Issued
- Issued on 5/22/2025
- Issuing Office
- Current Status
- Permit Finaled on 12/23/2025
Permit Application Status History
| Submitted | 7/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2024 | SERGIO GUTIERREZ |
| Assigned to Zoning Architect | 7/19/2024 | JASON BRAVO |
| Corrections Issued | 7/22/2024 | SERGIO GUTIERREZ |
| Quality Review Completed | 7/23/2024 | JOHNNY WU |
| Applicant returned to address corrections | 10/18/2024 | SERGIO GUTIERREZ |
| Plan Check Approved | 5/22/2025 | SERGIO GUTIERREZ |
| Issued | 5/22/2025 | APPLICANT |
| Permit Finaled | 12/19/2025 | RICARDO ROBLES |
Permit Application Clearance Information
| City owned building/parcel | Cleared | 7/31/2024 | SERGIO GUTIERREZ |
| Hold | Cleared | 10/16/2024 | MARIA VENDIVIL |
| Sewer availability | Cleared | 11/4/2024 | JILVER MAZARIEGOS |
| Port of LA Approval | Cleared | 12/24/2024 | CHRISTINA SAR |
| "Q" conditions | Cleared | 1/8/2025 | JACQUELINE TORRES |
| Coastal Zone | Cleared | 1/8/2025 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 1/8/2025 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 1/8/2025 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 1/8/2025 | JACQUELINE TORRES |
| Miscellaneous | Cleared | 1/8/2025 | JACQUELINE TORRES |
| Flood clearance | Cleared | 1/14/2025 | TUYEN LE |
| Miscellaneous | Cleared | 1/14/2025 | RONY GIRON |
| Eng Process Fee Ord 176,300 | Cleared | 1/15/2025 | JILVER MAZARIEGOS |
| Green Code | Cleared | 1/22/2025 | MICHAEL AYERS |
| DAS Clearance | Cleared | 2/4/2025 | Rosendo Medina |
| Food Service Establishment | Cleared | 3/27/2025 | STANLEY WING |
| Fire Marshal Fire Life Safety | Cleared | 4/29/2025 | RONILO MULAWIN |
| Zoning Plan Check | Cleared | 5/2/2025 | Rosendo Medina |
| Food establishment approval | Cleared | 5/22/2025 | LACDHS APPROVED |
Contact Information
| Contractor | Fulcrum Construction Inc; Lic. No.: 832993-B | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/27/2025 | Conditional Approval | JOEY BUCHANAN |
| Light Gage Steel Frame | 5/27/2025 | Partial Approval | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 5/29/2025 | Approved | JOEY BUCHANAN |
| Deputy Drilled-In Anchors | 6/4/2025 | Conditional Approval | RICARDO ROBLES |
| Deputy Other (see comments) | 6/4/2025 | Conditional Approval | RICARDO ROBLES |
| Drywall Nailing | 6/12/2025 | Partial Approval | RICARDO ROBLES |
| Insulation | 6/12/2025 | Approved | RICARDO ROBLES |
| Light Gage Steel Frame | 6/12/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 7/17/2025 | Partial Approval | RICARDO ROBLES |
| Drywall Nailing | 7/29/2025 | Partial Approval | RICARDO ROBLES |
| Light Gage Steel Frame | 11/24/2025 | Partial Approval | DAVID TSAU |
| Green Building Final | 12/17/2025 | Approved | RICARDO ROBLES |
| SGSOV-Seismic Gas S/O Valve | 12/17/2025 | SGSOV Approved | RICARDO ROBLES |
| Smoke Detectors | 12/17/2025 | Approved | RICARDO ROBLES |
| T-Bar Ceiling | 12/17/2025 | Approved | RICARDO ROBLES |
| Final | 12/18/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Special/Order Compliance | 12/18/2025 | Partial Inspection | REGINA MENDEZ |
| Final | 12/19/2025 | Permit Finaled | RICARDO ROBLES |