1545 W 214TH ST 90501
Certificate Information: 1545 W 214TH ST 90501
- Application / Permit
- 24016-10000-21952
- Plan Check / Job No.
- B24LA13107
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert detached Garage to Accessory Dwelling Unit CA G.C. 65852.2(e)(1)(A) . Work per wood frame prescriptive provisions R3 occupancy
- Permit Issued
- Issued on 11/5/2024
- Issuing Office
- Current Status
- CofO Issued on 12/17/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/16/2024 | GEORGE ALVAREZ |
| Corrections Issued | 7/17/2024 | GEORGE ALVAREZ |
| Applicant returned to address corrections | 9/25/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 10/7/2024 | KELVIN CHUONG |
| Plan Check Approved | 10/9/2024 | KELVIN CHUONG |
| Issued | 11/5/2024 | APPLICANT |
| CofO in Progress | 12/17/2025 | EUGENE CASSIDY |
| Permit Finaled | 12/17/2025 | ANSON MAGLASANG |
| CofO Issued | 12/17/2025 | ANSON MAGLASANG |
| Permit Finaled | 12/17/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 8/13/2024 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 8/16/2024 | KHAING AYE |
| Sewer availability | Cleared | 9/18/2024 | JILVER MAZARIEGOS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/14/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 12/10/2024 | Corrections Issued | EUGENE CASSIDY |
| Footing/Foundation/Slab | 12/23/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 6/16/2025 | Corrections Issued | EUGENE CASSIDY |
| ELECTRICAL-Rough | 7/8/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 7/8/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 7/29/2025 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 7/29/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 7/29/2025 | Approved | EUGENE CASSIDY |
| Insulation | 8/1/2025 | Corrections Issued | EUGENE CASSIDY |
| Insulation | 8/11/2025 | Corrections Issued | EUGENE CASSIDY |
| Insulation | 8/12/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 8/15/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 9/10/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/10/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 9/15/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 11/4/2025 | Corrections Issued | EUGENE CASSIDY |
| Final | 12/11/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 12/11/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/11/2025 | SGSOV Not Ready | EUGENE CASSIDY |
| Smoke Detectors | 12/11/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 12/15/2025 | Approved | EUGENE CASSIDY |
| Final | 12/15/2025 | OK to Issue CofO | EUGENE CASSIDY |
| Green Building Final | 12/15/2025 | Approved | EUGENE CASSIDY |
| HVAC-Final | 12/15/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 12/15/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/15/2025 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 12/15/2025 | Approved | EUGENE CASSIDY |