1217 3/4 N WATERLOO ST 90026

Certificate Information: 1217 3/4 N WATERLOO ST 90026

Application / Permit
24016-10000-21715
Plan Check / Job No.
B24LA12951
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan: Conversion of (E) detached garage into an 340 sf ADU. Per CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 3/20/2025
Issuing Office
Current Status
Issued on 3/20/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 7/8/2024 APPLICANT
Assigned to Plan Check Engineer 7/10/2024 ALFREDO JARA
Corrections Issued 7/11/2024 ALFREDO JARA
Applicant returned to address corrections 11/15/2024 ALFREDO JARA
Applicant returned to address corrections 11/26/2024 KAVIAN REFAHI
Applicant returned to address corrections 12/23/2024 ALFREDO JARA
Applicant returned to address corrections 1/21/2025 YASHAR EMAMI
Applicant returned to address corrections 1/30/2025 DAVID CASTILLO
Plan Check Approved 2/19/2025 DAVID CASTILLO
Issued 3/20/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 7/17/2024 WALLIE JONG
Roof/Waste drainage to street Cleared 7/17/2024 WALLIE JONG
Sewer availability Cleared 7/17/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/22/2024 WALLIE JONG
ZI Cleared 7/24/2024 MATHEW QUAN
Construction near power lines Cleared 11/3/2024 TINA MIRANDA
Construction within easement Cleared 11/3/2024 TINA MIRANDA
Grading Pre-Inspection Cleared 11/27/2024 ALFREDO JARA
Tenant Habitability Plan Cleared 1/13/2025 RICARDO BOHORQUEZ

Contact Information

Contractor Owner-Builder       ,
Engineer Watson,, Darren; Lic. No.: C87717 1759 HAPPY TRAIL      TOPANGA, CA 90290
Engineer Watson,, Darren; Lic. No.: NA87717       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Wood Frame 6/12/2026    Time Frame: 11-1

Inspection Request History

PLUMBING-Rough 6/4/2025 Partial Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 6/17/2025 Conditional Approval HAMIK HARTOUNIAN
Deputy Drilled-In Anchors 6/18/2025 No Access for Inspection WILLIAM SIERRA
Deputy Drilled-In Anchors 6/20/2025 Conditional Approval ALEX COLIN
Footing/Foundation/Slab 6/20/2025 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 7/7/2025 Corrections Issued BRENDAN MORELLI
Footing/Foundation/Slab 7/21/2025 Approved HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/11/2026 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Rough 3/11/2026 Corrections Issued HAMIK HARTOUNIAN
BUILDING-Rough-Frame 3/27/2026 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 3/27/2026 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 3/27/2026 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/1/2026 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 5/7/2026 Partial Approval HAMIK HARTOUNIAN