8835-8837 S KITTYHAWK AVE 90045

Certificate Information: 8835-8837 S KITTYHAWK AVE 90045

Application / Permit
24016-10000-21386
Plan Check / Job No.
B24LA12697
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Addition and remodel (E) SFD. Cnversion of (E) Garage to ADU and addition to ADU to build a 638 sf ADU. . PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 11/5/2024
Issuing Office
Current Status
CofO Issued on 11/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/2/2024 APPLICANT
Assigned to Plan Check Engineer 7/8/2024 ALFREDO JARA
Corrections Issued 7/9/2024 ALFREDO JARA
Plan Check Approved 9/8/2024 ALFREDO JARA
Issued 11/5/2024 APPLICANT
CofO in Progress 11/3/2025 JESUS PINEDA
Permit Finaled 11/6/2025 RICHARD STEINBACH
CofO Issued 11/6/2025 RICHARD STEINBACH
Permit Finaled 11/6/2025 RICHARD STEINBACH

Permit Application Clearance Information

ZA Case Cleared 8/6/2024 RUBEN VASQUEZ
Address approval Cleared 8/21/2024 DARIN LAM
Eng Process Fee Ord 176,300 Cleared 8/22/2024 DARIN LAM
Sewer availability Cleared 8/22/2024 DARIN LAM
Roof/Waste drainage to street Cleared 8/28/2024 DIANA RENTERIA
Specific Plan Cleared 9/5/2024 PEDRO AYALA

Contact Information

Architect Maclaury,, Maria Isabel; Lic. No.: NA31836       ,
Contractor All Building & Construction Inc; Lic. No.: 1040335-B       ,
Engineer Shmeit,, Ayman Ivan; Lic. No.: C93325 9744 MAPLE ST #101      BELLFLOWER, CA 90706

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 12/26/2024 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 12/27/2024 Partial Approval JESUS PINEDA
PLUMBING-Rough 1/30/2025 Partial Approval TEMISTOCLES CAAL
Sewer 1/30/2025 Approved TEMISTOCLES CAAL
Deputy Drilled-In Anchors 2/4/2025 Conditional Approval TEMISTOCLES CAAL
Footing/Foundation/Slab 2/6/2025 Approved BOBBY KEY
Special/Order Compliance 2/6/2025 Partial Inspection TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 2/11/2025 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Partial Approval BOBBY KEY
Gas Test 3/13/2025 Not Ready for Inspection JAYLIN GRAVITTE
Deputy Drilled-In Anchors 3/20/2025 Conditional Approval JESUS PINEDA
Gas Test 3/24/2025 Partial Inspection JESUS PINEDA
Gas Test 3/25/2025 Partial Approval JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/4/2025 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 6/20/2025 Approved BOBBY KEY
HVAC-Rough 6/20/2025 Corrections Issued BOBBY KEY
Interior/Exterior Lathing 6/20/2025 Partial Approval BOBBY KEY
PLUMBING-Rough 6/20/2025 Approved BOBBY KEY
BUILDING-Rough-Frame 7/8/2025 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 7/8/2025 Corrections Issued JESUS PINEDA
Green Building Rough 7/8/2025 Approved JESUS PINEDA
HVAC-Rough 7/8/2025 Approved JESUS PINEDA
Shower Pan 7/8/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 7/10/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 7/10/2025 Approved ANTHONY EGSON
Green Building Rough 7/10/2025 Approved ANTHONY EGSON
Insulation 7/14/2025 Approved ANTHONY EGSON
Drywall Nailing 7/21/2025 Approved JAYLIN GRAVITTE
Interior/Exterior Lathing 7/21/2025 Approved JAYLIN GRAVITTE
ELECTRICAL-Final 10/28/2025 Approved JESUS PINEDA
Final 10/28/2025 Corrections Issued JESUS PINEDA
Green Building Final 10/28/2025 Approved JESUS PINEDA
HVAC-Final 10/28/2025 Approved JESUS PINEDA
PLUMBING-Final 10/28/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 10/28/2025 SGSOV Approved JESUS PINEDA
Service/Power Release 10/28/2025 Approved JESUS PINEDA
Smoke Detectors 10/28/2025 Approved JESUS PINEDA
Final 11/3/2025 OK to Issue CofO JESUS PINEDA