1260 W 39TH ST 1-6 90037
Certificate Information: 1260 W 39TH ST 1-6 90037
- Application / Permit
- 24016-10000-21355
- Plan Check / Job No.
- B24LA12679
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT PORTION OF 1ST FLOOR STORAGE AREA TO (N) ACCESSORY DWELLING UNIT IN AN (E) 2-STORY APARTMENT PER CA Govt. Code 65852.2(e)(1)(C). NO STRUCTURAL WORK.
- Permit Issued
- Issued on 10/29/2024
- Issuing Office
- Current Status
- CofO Issued on 9/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/8/2024 | MADISON ODELL |
| Corrections Issued | 7/9/2024 | MADISON ODELL |
| Applicant returned to address corrections | 9/11/2024 | MADISON ODELL |
| Applicant returned to address corrections | 10/2/2024 | MADISON ODELL |
| Plan Check Approved | 10/7/2024 | MADISON O'DELL |
| Issued | 10/29/2024 | APPLICANT |
| CofO in Progress | 9/23/2025 | ALFREDO LOPEZ |
| Permit Finaled | 9/23/2025 | ERNESTO CORRAL |
| CofO Issued | 9/23/2025 | ERNESTO CORRAL |
| Permit Finaled | 9/23/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| "Q" conditions | Cleared | 7/15/2024 | ROSALINDA MEZA |
| Address approval | Cleared | 7/15/2024 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2024 | JEANIE LAM |
| Sewer availability | Cleared | 7/15/2024 | JEANIE LAM |
| ZI | Cleared | 7/15/2024 | ROSALINDA MEZA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/27/2024 | Corrections Issued | DARRYL ARNOLD |
| Green Building Rough | 2/18/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 2/18/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Rough | 2/25/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 2/25/2025 | Partial Inspection | ALFREDO LOPEZ |
| Insulation | 3/3/2025 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 3/7/2025 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 3/11/2025 | Partial Approval | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 3/13/2025 | Partial Inspection | ALFREDO LOPEZ |
| Interior/Exterior Lathing | 3/17/2025 | Approved | ALFREDO LOPEZ |
| Final | 4/23/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Final | 4/23/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Rough | 4/23/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 4/23/2025 | SGSOV Approved | ALFREDO LOPEZ |
| Smoke Detectors | 4/23/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 4/23/2025 | Partial Approval | ALFREDO LOPEZ |
| Final | 6/4/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Final | 6/4/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Rough | 6/4/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Smoke Detectors | 6/4/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 6/4/2025 | Partial Inspection | ALFREDO LOPEZ |
| Final | 6/12/2025 | OK to Issue CofO | ALFREDO LOPEZ |
| Green Building Final | 6/12/2025 | Approved | ALFREDO LOPEZ |
| Green Building Rough | 6/12/2025 | Approved | ALFREDO LOPEZ |
| Smoke Detectors | 6/12/2025 | Approved | ALFREDO LOPEZ |
| Wood Frame | 6/12/2025 | Approved | ALFREDO LOPEZ |