1967 N DRACENA DR 90027
Certificate Information: 1967 N DRACENA DR 90027
- Application / Permit
- 24016-10000-21336
- Plan Check / Job No.
- B24LA12668
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO A (N) ACCESSORY DWELLING UNIT PER CA GOVT. CODE 65852.2(e)(1)(D) AND APPLICABLE PART OF LAMC 12.22A.33(c)-(d),(g).
- Permit Issued
- Issued on 12/16/2024
- Issuing Office
- Current Status
- CofO Issued on 10/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/8/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/10/2024 | GIOVANNY CHAVEZ |
| Corrections Issued | 7/11/2024 | GIOVANNY CHAVEZ |
| Plan Check Approved | 10/2/2024 | KAMYAR EMAMI |
| Issued | 12/16/2024 | APPLICANT |
| CofO in Progress | 9/30/2025 | ENRIQUE MIRELES |
| Permit Finaled | 10/4/2025 | DEROLD HAUFF |
| CofO Issued | 10/4/2025 | DEROLD HAUFF |
| Permit Finaled | 10/4/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| ZA Case | Cleared | 7/17/2024 | DANIEL CORONADO |
| ZA Case | Cleared | 7/17/2024 | DANIEL CORONADO |
| Address approval | Cleared | 7/18/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 7/18/2024 | TREVOR QUAN |
| Grading Pre-Inspection | Cleared | 7/22/2024 | LANNY MERRICK |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2024 | TREVOR QUAN |
| Construction near power lines | Cleared | 8/21/2024 | THERESA NGUYEN |
Contact Information
| Contractor | Quantum Construction & Design; Lic. No.: 1061867-B | , |
| Engineer | Adzhemyan,, Arsen; Lic. No.: C89103 | 1010 RALEIGH ST APT 107 GLENDALE, CA 91205 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/15/2025 | Conditional Approval | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 1/15/2025 | Not Ready for Inspection | NICHOLAS LOPEZ |
| Excavation/Setback/Form/Re-Bar | 1/23/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Underground Mechanical | 1/23/2025 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 1/27/2025 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 1/27/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 2/27/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2025 | Corrections Issued | ENRIQUE MIRELES |
| HVAC-Rough | 2/27/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 2/27/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 3/3/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Approved | ENRIQUE MIRELES |
| Green Building Rough | 3/3/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 3/3/2025 | Approved | ENRIQUE MIRELES |
| Insulation | 3/18/2025 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/20/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Drywall Nailing | 3/24/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 3/24/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Sewer | 3/24/2025 | Approved | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 4/16/2025 | No Access for Inspection | JOSH MEISTER |
| Interior/Exterior Lathing | 4/18/2025 | Corrections Issued | ENRIQUE MIRELES |
| Interior/Exterior Lathing | 5/6/2025 | Partial Approval | ALEX COLIN |
| Interior/Exterior Lathing | 5/27/2025 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 8/27/2025 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 8/28/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/9/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 9/9/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Final | 9/9/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 9/9/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 9/9/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 9/9/2025 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/9/2025 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/10/2025 | Corrections Issued | NICHOLAS LOPEZ |
| HVAC-Final | 9/10/2025 | Corrections Issued | NICHOLAS LOPEZ |
| PLUMBING-Final | 9/10/2025 | Corrections Issued | NICHOLAS LOPEZ |
| ELECTRICAL-Final | 9/16/2025 | Approved | ENRIQUE MIRELES |
| Final | 9/16/2025 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 9/16/2025 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 9/16/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 9/16/2025 | Approved | ENRIQUE MIRELES |
| Smoke Detectors | 9/16/2025 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 9/23/2025 | Approved | ENRIQUE MIRELES |
| Final | 9/23/2025 | OK to Issue CofO | ENRIQUE MIRELES |
| HVAC-Final | 9/23/2025 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 9/23/2025 | Approved | ENRIQUE MIRELES |