23324-23326 S MALTBY PL 90710
Certificate Information: 23324-23326 S MALTBY PL 90710
- Application / Permit
- 24016-10000-21200
- Plan Check / Job No.
- B24LA12584
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT (416 SQ.FT) PER CA Govt. Code 65852.2(e)(1)(A).
- Permit Issued
- Issued on 2/18/2025
- Issuing Office
- Current Status
- CofO Issued on 11/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/5/2024 | SARKIS HARABEDIAN |
| Corrections Issued | 7/8/2024 | SARKIS HARABEDIAN |
| Plan Check Approved | 7/31/2024 | SARKIS HARABEDIAN |
| Issued | 2/18/2025 | APPLICANT |
| CofO in Progress | 10/30/2025 | EUGENE CASSIDY |
| Permit Finaled | 11/3/2025 | ANSON MAGLASANG |
| CofO Issued | 11/3/2025 | ANSON MAGLASANG |
| Permit Finaled | 11/3/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 7/15/2024 | KHAING AYE |
| Eng Process Fee Ord 176,300 | Cleared | 7/26/2024 | ERIK BEASLEY |
| Sewer availability | Cleared | 7/26/2024 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/25/2025 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 2/25/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 3/5/2025 | Partial Approval | EUGENE CASSIDY |
| ELECTRICAL-Rough | 4/16/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 4/16/2025 | Corrections Issued | EUGENE CASSIDY |
| PLUMBING-Rough | 4/16/2025 | Corrections Issued | EUGENE CASSIDY |
| Shower Pan | 4/16/2025 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 5/1/2025 | Partial Approval | EUGENE CASSIDY |
| Green Building Rough | 5/1/2025 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 5/1/2025 | Approved | EUGENE CASSIDY |
| Interior/Exterior Lathing | 5/1/2025 | Partial Approval | EUGENE CASSIDY |
| METHANE-Rough | 5/1/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 5/1/2025 | Approved | EUGENE CASSIDY |
| Insulation | 6/13/2025 | Partial Approval | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/13/2025 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 6/23/2025 | Approved | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2025 | Approved | EUGENE CASSIDY |
| Insulation | 6/23/2025 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 7/7/2025 | Partial Approval | EUGENE CASSIDY |
| Final | 9/29/2025 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/29/2025 | Approved | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 9/29/2025 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 9/29/2025 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 10/29/2025 | Approved | EUGENE CASSIDY |
| Final | 10/29/2025 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 10/29/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 10/29/2025 | Approved | EUGENE CASSIDY |