23324-23326 S MALTBY PL 90710

Certificate Information: 23324-23326 S MALTBY PL 90710

Application / Permit
24016-10000-21200
Plan Check / Job No.
B24LA12584
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT THE (E) ATTACHED GARAGE INTO AN ACCESSORY DWELLING UNIT (416 SQ.FT) PER CA Govt. Code 65852.2(e)(1)(A).
Permit Issued
Issued on 2/18/2025
Issuing Office
Current Status
CofO Issued on 11/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/3/2024 APPLICANT
Assigned to Plan Check Engineer 7/5/2024 SARKIS HARABEDIAN
Corrections Issued 7/8/2024 SARKIS HARABEDIAN
Plan Check Approved 7/31/2024 SARKIS HARABEDIAN
Issued 2/18/2025 APPLICANT
CofO in Progress 10/30/2025 EUGENE CASSIDY
Permit Finaled 11/3/2025 ANSON MAGLASANG
CofO Issued 11/3/2025 ANSON MAGLASANG
Permit Finaled 11/3/2025 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 7/15/2024 KHAING AYE
Eng Process Fee Ord 176,300 Cleared 7/26/2024 ERIK BEASLEY
Sewer availability Cleared 7/26/2024 ERIK BEASLEY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

EUGENE CASSIDY, (310) 548-2508 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/25/2025 Conditional Approval ANSON MAGLASANG
Footing/Foundation/Slab 2/25/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 3/5/2025 Partial Approval EUGENE CASSIDY
ELECTRICAL-Rough 4/16/2025 Approved EUGENE CASSIDY
HVAC-Rough 4/16/2025 Corrections Issued EUGENE CASSIDY
PLUMBING-Rough 4/16/2025 Corrections Issued EUGENE CASSIDY
Shower Pan 4/16/2025 Approved EUGENE CASSIDY
BUILDING-Rough-Frame 5/1/2025 Partial Approval EUGENE CASSIDY
Green Building Rough 5/1/2025 Approved EUGENE CASSIDY
HVAC-Rough 5/1/2025 Approved EUGENE CASSIDY
Interior/Exterior Lathing 5/1/2025 Partial Approval EUGENE CASSIDY
METHANE-Rough 5/1/2025 Approved EUGENE CASSIDY
PLUMBING-Rough 5/1/2025 Approved EUGENE CASSIDY
Insulation 6/13/2025 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 6/13/2025 Partial Approval JOSEPH MCGARRY
BUILDING-Rough-Frame 6/23/2025 Approved EUGENE CASSIDY
Floor/Roof Diaphrgm/Shear Wall 6/23/2025 Approved EUGENE CASSIDY
Insulation 6/23/2025 Approved EUGENE CASSIDY
Drywall Nailing 7/7/2025 Partial Approval EUGENE CASSIDY
Final 9/29/2025 Corrections Issued EUGENE CASSIDY
Green Building Final 9/29/2025 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 9/29/2025 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 9/29/2025 Approved EUGENE CASSIDY
ELECTRICAL-Final 10/29/2025 Approved EUGENE CASSIDY
Final 10/29/2025 OK to Issue CofO EUGENE CASSIDY
HVAC-Final 10/29/2025 Approved EUGENE CASSIDY
PLUMBING-Final 10/29/2025 Approved EUGENE CASSIDY