10511 W VERONA AVE 90025
Certificate Information: 10511 W VERONA AVE 90025
- Application / Permit
- 24016-10000-21180
- Plan Check / Job No.
- B24LA12562
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Eplan Convert existing detached garage into an ADU per ordinance
- Permit Issued
- Issued on 10/10/2024
- Issuing Office
- Current Status
- CofO Issued on 6/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/1/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/5/2024 | JOHN MESIAS |
| Corrections Issued | 7/6/2024 | JOHN MESIAS |
| Applicant returned to address corrections | 7/26/2024 | LUKE GONZALES |
| Plan Check Approved | 8/20/2024 | LUKE GONZALES |
| Issued | 10/10/2024 | APPLICANT |
| CofO in Progress | 5/21/2025 | DANIEL VERA |
| Permit Finaled | 6/3/2025 | RICHARD STEINBACH |
| CofO Issued | 6/3/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/3/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Sewer availability | Cleared | 7/16/2024 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2024 | DINAH GARIN |
| Address approval | Cleared | 7/23/2024 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 7/23/2024 | DINAH GARIN |
| Grading Pre-Inspection | Cleared | 7/23/2024 | VASIL MIHALEV |
| Specific Plan | Cleared | 7/24/2024 | HAMID GHAEMMAGHAMI |
Contact Information
| Architect | Augustin,, Valery; Lic. No.: NA32614 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/12/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 11/12/2024 | Partial Approval | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 11/18/2024 | Approved | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 11/19/2024 | Approved | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/19/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/28/2025 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/28/2025 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 1/28/2025 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 1/28/2025 | Conditional Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/10/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 2/20/2025 | Partial Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/20/2025 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 2/20/2025 | Corrections Issued | STEPHANIE SWANSON |
| Insulation | 2/25/2025 | Approved | SEAN HAUPT |
| Shower Pan | 2/25/2025 | Approved | SEAN HAUPT |
| Floor/Roof Diaphrgm/Shear Wall | 3/3/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/4/2025 | Approved | BOBBY KEY |
| Rough-Elec/Plmb/HVAC | 3/4/2025 | Partial Approval | BOBBY KEY |
| Drywall Nailing | 3/7/2025 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 5/1/2025 | SGSOV Not Ready | DANIEL VERA |
| Final | 5/13/2025 | Corrections Issued | DANIEL VERA |
| METHANE-Final | 5/13/2025 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 5/13/2025 | SGSOV Approved | DANIEL VERA |
| Smoke Detectors | 5/13/2025 | Approved | DANIEL VERA |
| Final | 5/15/2025 | OK to Issue CofO | MEL KHACHATOURIAN |