4657 W COUNCIL ST 90004

Certificate Information: 4657 W COUNCIL ST 90004

Application / Permit
24016-10000-20772
Plan Check / Job No.
B24LA12246
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan. Convert (e) rec-room with attached garage to an ADU with attached garage per LAMC 12.22 A.33(b)(1)
Permit Issued
Issued on 7/25/2025
Issuing Office
Current Status
CofO Issued on 1/13/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2024 APPLICANT
Assigned to Plan Check Engineer 7/1/2024 YASHAR EMAMI
Corrections Issued 7/17/2024 YASHAR EMAMI
Applicant returned to address corrections 7/9/2025 REZA HAGHIGHAT
Plan Check Approved 7/16/2025 REZA HAGHIGHAT
Issued 7/25/2025 APPLICANT
CofO in Progress 1/12/2026 JEFFREY MEAD
Permit Finaled 1/13/2026 DEROLD HAUFF
CofO Issued 1/13/2026 DEROLD HAUFF
Permit Finaled 1/13/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 4/29/2025 JEREMY CHOK
Eng Process Fee Ord 176,300 Cleared 4/29/2025 JEREMY CHOK
Sewer availability Cleared 4/29/2025 JEREMY CHOK
HPOZ Cleared 7/1/2025 RAFAEL FONTES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/12/2025 Approved JEFFREY MEAD
Pre-Inspection 9/4/2025 Not Ready for Inspection JEFFREY MEAD
Drywall Nailing 9/25/2025 Not Ready for Inspection GEM DE OCAMPO
Insulation 9/25/2025 Not Ready for Inspection GEM DE OCAMPO
PLUMBING-Rough 9/25/2025 Corrections Issued GEM DE OCAMPO
ELECTRICAL-Rough 10/3/2025 Corrections Issued JOSH MEISTER
HVAC-Rough 10/3/2025 Corrections Issued JOSH MEISTER
PLUMBING-Rough 10/3/2025 Corrections Issued JOSH MEISTER
ELECTRICAL-Rough 10/10/2025 Corrections Issued JEFFREY MEAD
HVAC-Rough 10/10/2025 Corrections Issued JEFFREY MEAD
PLUMBING-Rough 10/10/2025 Corrections Issued JEFFREY MEAD
BUILDING-Rough-Frame 10/28/2025 Corrections Issued JEFFREY MEAD
ELECTRICAL-Rough 10/28/2025 Partial Approval JEFFREY MEAD
Insulation 10/28/2025 Not Ready for Inspection JEFFREY MEAD
PLUMBING-Rough 10/28/2025 Not Ready for Inspection JEFFREY MEAD
Shower Pan 10/28/2025 Not Ready for Inspection JEFFREY MEAD
ELECTRICAL-Rough 11/6/2025 Conditional Approval JEFFREY MEAD
Insulation 11/6/2025 Approved JEFFREY MEAD
PLUMBING-Rough 11/6/2025 Approved JEFFREY MEAD
Wood Frame 11/6/2025 Approved JEFFREY MEAD
Drywall Nailing 11/20/2025 Corrections Issued JEFFREY MEAD
HVAC-Rough 11/20/2025 Approved JEFFREY MEAD
Wood Frame 11/20/2025 Not Ready for Inspection JEFFREY MEAD
Drywall Nailing 11/25/2025 Approved JEFFREY MEAD
Wood Frame 11/25/2025 Approved JEFFREY MEAD
BUILDING-Rough-Frame 12/11/2025 Approved JEFFREY MEAD
Final 12/11/2025 Corrections Issued JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 12/11/2025 SGSOV Not Ready JEFFREY MEAD
Smoke Detectors 12/11/2025 Approved JEFFREY MEAD
Final 1/5/2026 Not Ready for Inspection JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 1/5/2026 SGSOV Approved JEFFREY MEAD
Final 1/9/2026 OK to Issue CofO JEFFREY MEAD