205 N ROBINSON ST 90026

Certificate Information: 205 N ROBINSON ST 90026

Application / Permit
24016-10000-20746
Plan Check / Job No.
B24LA12228
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT ACCESSORY LIVING QUARTERS INTO A DETACHED ADU PER STATE LAW CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 7/22/2024
Issuing Office
Metro
Current Status
CofO Issued on 9/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/26/2024 APPLICANT
Assigned to Plan Check Engineer 6/27/2024 SAMUEL GONZALEZ
Corrections Issued 6/29/2024 SAMUEL GONZALEZ
Plan Check Approved 7/18/2024 YAQUB MIRZA
Issued 7/22/2024 APPLICANT
CofO in Progress 9/12/2025 FREDDIE RIVERA
Permit Finaled 9/13/2025 DEROLD HAUFF
CofO Issued 9/13/2025 DEROLD HAUFF
Permit Finaled 9/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/5/2024 CHRISTINA BRACO
Sewer availability Cleared 7/5/2024 CHRISTINA BRACO
Eng Process Fee Ord 176,300 Cleared 7/9/2024 CHRISTINA BRACO
Construction near power lines Cleared 7/16/2024 EDGAR PASCUA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/6/2024 No Access for Inspection FREDDIE RIVERA
Pre-Inspection 9/10/2024 Not Ready for Inspection THOMAS LOGRASSO
Deputy Drilled-In Anchors 10/4/2024 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 10/8/2024 Corrections Issued FREDDIE RIVERA
PLUMBING-Rough 10/8/2024 Partial Approval FREDDIE RIVERA
Footing/Foundation/Slab 10/18/2024 Corrections Issued ALIZAH MAYAGOITIA
Deputy Drilled-In Anchors 10/24/2024 Conditional Approval JOHN QUINTANILLA
Excavation/Setback/Form/Re-Bar 11/1/2024 Approved WILLIAM SIERRA
BUILDING-Rough-Frame 3/6/2025 Partial Inspection FREDDIE RIVERA
ELECTRICAL-Rough 3/6/2025 Approved FREDDIE RIVERA
HVAC-Rough 3/6/2025 Corrections Issued FREDDIE RIVERA
METHANE-Rough 3/6/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 3/6/2025 Partial Inspection FREDDIE RIVERA
HVAC-Rough 4/30/2025 Approved FREDDIE RIVERA
PLUMBING-Rough 4/30/2025 Corrections Issued FREDDIE RIVERA
BUILDING-Rough-Frame 5/2/2025 Approved FREDDIE RIVERA
Green Building Rough 5/2/2025 Approved FREDDIE RIVERA
Insulation 5/5/2025 Approved REGINA MENDEZ
Sewer 5/5/2025 Not Ready for Inspection REGINA MENDEZ
Drywall Nailing 5/14/2025 Approved FREDDIE RIVERA
Interior/Exterior Lathing 5/14/2025 Approved FREDDIE RIVERA
Shower Pan 5/14/2025 Approved FREDDIE RIVERA
Underground Mechanical 5/14/2025 Partial Approval FREDDIE RIVERA
Final 7/2/2025 Not Ready for Inspection ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 7/2/2025 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 7/2/2025 Approved ARTHUR NEGRETE
Final 7/15/2025 Corrections Issued FREDDIE RIVERA
Final 9/12/2025 OK to Issue CofO FREDDIE RIVERA