2353 E SHERIDAN ST 90033
Certificate Information: 2353 E SHERIDAN ST 90033
- Application / Permit
- 24016-10000-20481
- Plan Check / Job No.
- B24LA12069
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) - PER WFPP *Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2).
- Permit Issued
- Issued on 1/3/2025
- Issuing Office
- Current Status
- CofO Issued on 6/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/28/2024 | CAROLEAN BASMA |
| Corrections Issued | 6/29/2024 | CAROLEAN BASMA |
| Applicant returned to address corrections | 9/4/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 1/2/2025 | DANIEL ABRAMYAN |
| Issued | 1/3/2025 | APPLICANT |
| CofO in Progress | 6/18/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 6/21/2025 | DEROLD HAUFF |
| CofO Issued | 6/21/2025 | DEROLD HAUFF |
| Permit Finaled | 6/21/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/8/2024 | AMBER CAMPBELL |
| Clean Up Green Up | Cleared | 7/8/2024 | RUBEN VASQUEZ |
| Sewer availability | Cleared | 7/8/2024 | AMBER CAMPBELL |
| Eng Process Fee Ord 176,300 | Cleared | 7/10/2024 | AMBER CAMPBELL |
| Grading Pre-Inspection | Cleared | 10/2/2024 | MICHAEL TEMPLE |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/3/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/19/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 2/19/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Sewer | 2/19/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/1/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Rough | 4/1/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 4/1/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Underground Mechanical | 4/1/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/8/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 4/8/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 4/8/2025 | Approved | ALIZAH MAYAGOITIA |
| METHANE-Rough | 4/8/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/8/2025 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 4/10/2025 | Approved | JOSH MEISTER |
| BUILDING-Rough-Frame | 4/14/2025 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 4/17/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 5/28/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Final | 5/28/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 5/28/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| HVAC-Final | 5/28/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 5/28/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 5/28/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Smoke Detectors | 5/28/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/5/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Final | 6/5/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 6/5/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 6/18/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |