2353 E SHERIDAN ST 90033

Certificate Information: 2353 E SHERIDAN ST 90033

Application / Permit
24016-10000-20481
Plan Check / Job No.
B24LA12069
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) - PER WFPP *Existing construction that does not pose a threat to the publics health and safety was allowed per Government Code Section 55.852.2(d)(2).
Permit Issued
Issued on 1/3/2025
Issuing Office
Current Status
CofO Issued on 6/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/24/2024 APPLICANT
Assigned to Plan Check Engineer 6/28/2024 CAROLEAN BASMA
Corrections Issued 6/29/2024 CAROLEAN BASMA
Applicant returned to address corrections 9/4/2024 DANIEL ABRAMYAN
Plan Check Approved 1/2/2025 DANIEL ABRAMYAN
Issued 1/3/2025 APPLICANT
CofO in Progress 6/18/2025 ALIZAH MAYAGOITIA
Permit Finaled 6/21/2025 DEROLD HAUFF
CofO Issued 6/21/2025 DEROLD HAUFF
Permit Finaled 6/21/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/8/2024 AMBER CAMPBELL
Clean Up Green Up Cleared 7/8/2024 RUBEN VASQUEZ
Sewer availability Cleared 7/8/2024 AMBER CAMPBELL
Eng Process Fee Ord 176,300 Cleared 7/10/2024 AMBER CAMPBELL
Grading Pre-Inspection Cleared 10/2/2024 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/3/2025 Corrections Issued ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/19/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 2/19/2025 Partial Approval ALIZAH MAYAGOITIA
Sewer 2/19/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/1/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Rough 4/1/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 4/1/2025 Partial Approval ALIZAH MAYAGOITIA
Underground Mechanical 4/1/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 4/8/2025 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 4/8/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 4/8/2025 Approved ALIZAH MAYAGOITIA
METHANE-Rough 4/8/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 4/8/2025 Approved ALIZAH MAYAGOITIA
Insulation 4/10/2025 Approved JOSH MEISTER
BUILDING-Rough-Frame 4/14/2025 Approved ALIZAH MAYAGOITIA
Drywall Nailing 4/17/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 5/28/2025 Partial Approval ALIZAH MAYAGOITIA
Final 5/28/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 5/28/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
HVAC-Final 5/28/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 5/28/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 5/28/2025 SGSOV Approved ALIZAH MAYAGOITIA
Smoke Detectors 5/28/2025 Approved ALIZAH MAYAGOITIA
Final 6/5/2025 Partial Approval ALIZAH MAYAGOITIA
Green Building Final 6/5/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 6/5/2025 Approved ALIZAH MAYAGOITIA
Final 6/18/2025 OK to Issue CofO ALIZAH MAYAGOITIA