12043 W MARINE ST 90066
Certificate Information: 12043 W MARINE ST 90066
- Application / Permit
- 24016-10000-20224
- Plan Check / Job No.
- B24LA11929
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERTING (E) GARAGE TO AN ADU PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g) -BLDG SPRINKLERED THRU-OUT
- Permit Issued
- Issued on 8/28/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/27/2024 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 7/1/2024 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 7/3/2024 | KEN GILL |
| Building Plans Picked Up | 7/5/2024 | APPLICANT |
| Plan Check Approved | 8/28/2024 | MAHNAZ NOURHASHEMI |
| Issued | 8/28/2024 | APPLICANT |
| Permit Finaled | 6/10/2025 | RICHARD STEINBACH |
| CofO Issued | 6/10/2025 | RICHARD STEINBACH |
| Permit Finaled | 6/10/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/3/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 7/3/2024 | WALTER RAMIREZ |
| Address approval | Cleared | 7/8/2024 | VLADIMIR ARUTYUNYAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/8/2024 | VLADIMIR ARUTYUNYAN |
| Roof/Waste drainage to street | Cleared | 7/8/2024 | VLADIMIR ARUTYUNYAN |
| Sewer availability | Cleared | 7/8/2024 | VLADIMIR ARUTYUNYAN |
| Specific Plan | Cleared | 7/11/2024 | RICHARD WOO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/18/2024 | Approved | DANIEL VERA |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2024 | Approved | DANIEL VERA |
| Interior/Exterior Lathing | 12/11/2024 | Partial Approval | CARLOS MATAMOROS |
| Wood Frame | 12/11/2024 | Corrections Issued | CARLOS MATAMOROS |
| Insulation | 12/16/2024 | Partial Approval | REGINA MENDEZ |
| Special/Order Compliance | 12/16/2024 | Partial Inspection | BOBBY KEY |
| Special/Order Compliance | 12/16/2024 | Partial Inspection | JAYLIN GRAVITTE |
| Wood Frame | 12/17/2024 | Approved | DANIEL VERA |
| Insulation | 12/20/2024 | Approved | DANIEL VERA |
| Drywall Nailing | 12/27/2024 | Approved | KIRK SANDERS |
| Interior/Exterior Lathing | 1/2/2025 | Approved | REGINA MENDEZ |
| Special/Order Compliance | 1/2/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Final | 5/23/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Final | 5/23/2025 | Approved | WILBER ROSALES |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Approved | WILBER ROSALES |
| Smoke Detectors | 5/23/2025 | Approved | WILBER ROSALES |
| Final | 6/5/2025 | Conditional Approval | WILBER ROSALES |