19823-19825 S HAMILTON AVE 90502

Certificate Information: 19823-19825 S HAMILTON AVE 90502

Application / Permit
24016-10000-20213
Plan Check / Job No.
B24LA11924
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(12) Manufacturing
Work Description
(ePLAN) Tenant improvement within the existing warehouse/office to expand office space. No additional square footage.
Permit Issued
Issued on 12/5/2024
Issuing Office
Current Status
CofO Issued on 5/30/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2024 APPLICANT
Assigned to Plan Check Engineer 6/27/2024 VICTOR CHEN
Corrections Issued 6/29/2024 VICTOR CHEN
Quality Review Completed 7/15/2024 CAROLYNN NEPOMUCENO
Applicant returned to address corrections 9/4/2024 VICTOR CHEN
Applicant returned to address corrections 10/2/2024 VICTOR CHEN
Applicant returned to address corrections 10/17/2024 VICTOR CHEN
Assigned to Zoning Architect 10/23/2024 LY CHEA
Applicant returned to address corrections 11/19/2024 VICTOR CHEN
Applicant returned to address corrections 11/21/2024 VICTOR CHEN
Applicant returned to address corrections 12/2/2024 VICTOR CHEN
Plan Check Approved 12/4/2024 VICTOR CHEN
No Progress 12/4/2024 VICTOR CHEN
Plan Check Approved 12/4/2024 VICTOR CHEN
Issued 12/5/2024 APPLICANT
Permit Finaled 5/30/2025 JOEY BUCHANAN
CofO Issued 5/30/2025 JOEY BUCHANAN
Permit Finaled 5/30/2025 JOEY BUCHANAN

Permit Application Clearance Information

DAS Clearance Cleared 9/12/2024 Samuel Gonzalez
Green Code Cleared 10/25/2024 MICHAEL MARTINEZ
Zoning Plan Check Cleared 11/12/2024 Samuel Gonzalez

Contact Information

Architect Cataldo,, John G; Lic. No.: C10457 835 MISSION STREET      SOUTH PASADENA, CA 91030
Architect Cataldo,, John G; Lic. No.: NA10457       ,
Contractor Advanced Contractors Inc; Lic. No.: 382163-B       ,

Inspector Information

MICHAEL PETRUSKO, (310) 732-4552 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/6/2024 Approved MICHAEL PETRUSKO
Light Gage Steel Frame 12/6/2024 Approved MICHAEL PETRUSKO
Drywall Nailing 12/11/2024 Approved MICHAEL PETRUSKO
Final 5/21/2025 Conditional Approval MICHAEL PETRUSKO
Green Building Final 5/21/2025 Approved MICHAEL PETRUSKO
Green Building Rough 5/21/2025 Approved MICHAEL PETRUSKO
SGSOV-Seismic Gas S/O Valve 5/21/2025 SGSOV Approved MICHAEL PETRUSKO
Smoke Detectors 5/21/2025 Approved MICHAEL PETRUSKO
Wood Frame 5/21/2025 Approved MICHAEL PETRUSKO