ePlan CONVERT (E) DETACHED GARAGE TO ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 4/9/2025
Issuing Office
Current Status
CofO Issued on 3/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/7/2024 APPLICANT
Assigned to Plan Check Engineer 7/10/2024 ISIS ARGUETA
Corrections Issued 7/11/2024 ISIS ARGUETA
Applicant returned to address corrections 10/21/2024 ISIS ARGUETA
Plan Check Approved 4/2/2025 NAREG ATARIAN
Issued 4/9/2025 APPLICANT
CofO in Progress 2/27/2026 ARTHUR NEGRETE
Permit Finaled 3/10/2026 ANSON MAGLASANG
CofO Issued 3/10/2026 ANSON MAGLASANG
Permit Finaled 3/10/2026 ANSON MAGLASANG

Permit Application Clearance Information

Hold Cleared 9/5/2024 ALEXIS SCHULTZ
Sewer availability Cleared 9/11/2024 STEVE MELGAR
Public Works-Sewers Cleared 9/11/2024 STEVE MELGAR
Address approval Cleared 10/2/2024 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/3/2024 STEVE MELGAR
Construction near power lines Cleared 3/26/2025 EDGAR PASCUA

Contact Information

Contractor Owner-Builder       ,
Engineer Pinzon,, Eduardo Andres; Lic. No.: NA74869       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Gas Test 6/18/2025 Partial Inspection JOHN KLARIN
PLUMBING-Rough 6/18/2025 Partial Inspection JOHN KLARIN
Sewer 6/18/2025 Partial Inspection JOHN KLARIN
Footing/Foundation/Slab 6/24/2025 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 7/1/2025 Partial Inspection JOHN KLARIN
Footing/Foundation/Slab 7/10/2025 Approved JOHN KLARIN
BUILDING-Rough-Frame 8/14/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 8/14/2025 Corrections Issued ANTHONY EGSON
Green Building Rough 8/14/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 8/14/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 10/8/2025 Corrections Issued ANTHONY EGSON
PLUMBING-Rough 10/8/2025 Corrections Issued ANTHONY EGSON
Wood Frame 10/8/2025 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 10/15/2025 Not Ready for Inspection ANTHONY EGSON
PLUMBING-Rough 10/15/2025 Approved ANTHONY EGSON
Wood Frame 10/15/2025 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 10/31/2025 Corrections Issued ANTHONY EGSON
ELECTRICAL-Rough 10/31/2025 Not Ready for Inspection ANTHONY EGSON
Green Building Rough 10/31/2025 Approved ANTHONY EGSON
Wood Frame 10/31/2025 Not Ready for Inspection ANTHONY EGSON
Insulation 11/7/2025 Corrections Issued ANTHONY EGSON
BUILDING-Rough-Frame 11/13/2025 Approved ANTHONY EGSON
ELECTRICAL-Rough 11/13/2025 Approved ANTHONY EGSON
Insulation 11/18/2025 Partial Approval ANTHONY EGSON
Insulation 12/1/2025 Approved ARTHUR NEGRETE
Drywall Nailing 12/9/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 1/6/2026 Approved ARTHUR NEGRETE
Shower Pan 1/6/2026 Approved ARTHUR NEGRETE
Service/Power Release 1/15/2026 Not Ready for Inspection JOSEPH MCGARRY
Final 2/6/2026 Corrections Issued EUGENE CASSIDY
Green Building Final 2/6/2026 Not Ready for Inspection EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Not Ready EUGENE CASSIDY
Smoke Detectors 2/6/2026 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Final 2/11/2026 Approved ARTHUR NEGRETE
Final 2/11/2026 Corrections Issued ARTHUR NEGRETE
Green Building Final 2/11/2026 Approved ARTHUR NEGRETE
HVAC-Final 2/11/2026 Approved ARTHUR NEGRETE
PLUMBING-Final 2/11/2026 Approved ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 2/11/2026 SGSOV Approved ARTHUR NEGRETE
Smoke Detectors 2/11/2026 Approved ARTHUR NEGRETE
Final 2/26/2026 OK to Issue CofO ARTHUR NEGRETE
Service/Power Release 2/26/2026 Approved ARTHUR NEGRETE