5418 N NOBLE AVE 91411

Certificate Information: 5418 N NOBLE AVE 91411

Application / Permit
24016-10000-19717
Plan Check / Job No.
B24LA11606
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: Convert existing detached garage to new accessory dewlling unit per GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 7/31/2024
Issuing Office
Current Status
CofO Issued on 6/6/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/17/2024 APPLICANT
Assigned to Plan Check Engineer 6/21/2024 PINANK PATEL
Corrections Issued 6/22/2024 PINANK PATEL
Applicant returned to address corrections 7/4/2024 PINANK PATEL
Plan Check Approved 7/17/2024 GURUNATH NESARAJAH
Issued 7/31/2024 APPLICANT
CofO in Progress 5/21/2025 JACK KARGODORIAN
Permit Finaled 6/6/2025 RUBEN SALAS
CofO Issued 6/6/2025 RUBEN SALAS
Permit Finaled 6/6/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/28/2024 BRYAN GODINEZ
Sewer availability Cleared 6/28/2024 BRYAN GODINEZ
Eng Process Fee Ord 176,300 Cleared 7/3/2024 BRYAN GODINEZ

Contact Information

Contractor Go Home Builders Inc; Lic. No.: 1076807-B       ,
Engineer Hernandez, Sotomayor, Daniel; Lic. No.: C93095 15755 SATICOY ST APT#306      VAN NUYS, CA 91406

Inspector Information

RAUL OLAGI, (818) 374-1166 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/28/2024 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 9/3/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 9/3/2024 Partial Approval JACK KARGODORIAN
Deputy Drilled-In Anchors 9/16/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 10/1/2024 Corrections Issued JACK KARGODORIAN
ELECTRICAL-Rough 10/1/2024 Approved JACK KARGODORIAN
Green Building Rough 10/1/2024 Approved JACK KARGODORIAN
HVAC-Rough 10/1/2024 Approved JACK KARGODORIAN
PLUMBING-Rough 10/1/2024 Approved JACK KARGODORIAN
BUILDING-Rough-Frame 10/4/2024 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 10/9/2024 Partial Approval VINCENT HANLEY
Shower Pan 10/9/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 10/25/2024 Approved JACK KARGODORIAN
Insulation 10/25/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 10/25/2024 Partial Approval JACK KARGODORIAN
Drywall Nailing 12/3/2024 Approved JACK KARGODORIAN
Interior/Exterior Lathing 12/3/2024 Approved JACK KARGODORIAN
Gas Test 2/28/2025 Approved JACK KARGODORIAN
Sewer 2/28/2025 Approved JACK KARGODORIAN
Underground Mechanical 2/28/2025 Corrections Issued JACK KARGODORIAN
Gas Test 3/4/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 3/4/2025 Partial Approval JACK KARGODORIAN
Sewer 3/4/2025 Approved JACK KARGODORIAN
Underground Mechanical 3/4/2025 Approved JACK KARGODORIAN
PLUMBING-Rough 3/27/2025 Partial Approval JACK KARGODORIAN
Final 4/18/2025 Corrections Issued JACK KARGODORIAN
Green Building Final 4/18/2025 Not Ready for Inspection JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 4/18/2025 SGSOV Approved JACK KARGODORIAN
Smoke Detectors 4/18/2025 Approved JACK KARGODORIAN
ELECTRICAL-Final 5/16/2025 Approved JENNIFER RABUCHIN
Final 5/16/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 5/16/2025 Approved JENNIFER RABUCHIN
HVAC-Final 5/16/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/16/2025 Approved JENNIFER RABUCHIN