5418 N NOBLE AVE 91411
Certificate Information: 5418 N NOBLE AVE 91411
- Application / Permit
- 24016-10000-19717
- Plan Check / Job No.
- B24LA11606
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: Convert existing detached garage to new accessory dewlling unit per GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 7/31/2024
- Issuing Office
- Current Status
- CofO Issued on 6/6/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2024 | PINANK PATEL |
| Corrections Issued | 6/22/2024 | PINANK PATEL |
| Applicant returned to address corrections | 7/4/2024 | PINANK PATEL |
| Plan Check Approved | 7/17/2024 | GURUNATH NESARAJAH |
| Issued | 7/31/2024 | APPLICANT |
| CofO in Progress | 5/21/2025 | JACK KARGODORIAN |
| Permit Finaled | 6/6/2025 | RUBEN SALAS |
| CofO Issued | 6/6/2025 | RUBEN SALAS |
| Permit Finaled | 6/6/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2024 | BRYAN GODINEZ |
| Sewer availability | Cleared | 6/28/2024 | BRYAN GODINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2024 | BRYAN GODINEZ |
Contact Information
| Contractor | Go Home Builders Inc; Lic. No.: 1076807-B | , |
| Engineer | Hernandez, Sotomayor, Daniel; Lic. No.: C93095 | 15755 SATICOY ST APT#306 VAN NUYS, CA 91406 |
Inspector Information
| RAUL OLAGI, (818) 374-1166 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 8/28/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 9/3/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 9/3/2024 | Partial Approval | JACK KARGODORIAN |
| Deputy Drilled-In Anchors | 9/16/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 10/1/2024 | Corrections Issued | JACK KARGODORIAN |
| ELECTRICAL-Rough | 10/1/2024 | Approved | JACK KARGODORIAN |
| Green Building Rough | 10/1/2024 | Approved | JACK KARGODORIAN |
| HVAC-Rough | 10/1/2024 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 10/1/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 10/4/2024 | Partial Approval | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/9/2024 | Partial Approval | VINCENT HANLEY |
| Shower Pan | 10/9/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 10/25/2024 | Approved | JACK KARGODORIAN |
| Insulation | 10/25/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 10/25/2024 | Partial Approval | JACK KARGODORIAN |
| Drywall Nailing | 12/3/2024 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 12/3/2024 | Approved | JACK KARGODORIAN |
| Gas Test | 2/28/2025 | Approved | JACK KARGODORIAN |
| Sewer | 2/28/2025 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 2/28/2025 | Corrections Issued | JACK KARGODORIAN |
| Gas Test | 3/4/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 3/4/2025 | Partial Approval | JACK KARGODORIAN |
| Sewer | 3/4/2025 | Approved | JACK KARGODORIAN |
| Underground Mechanical | 3/4/2025 | Approved | JACK KARGODORIAN |
| PLUMBING-Rough | 3/27/2025 | Partial Approval | JACK KARGODORIAN |
| Final | 4/18/2025 | Corrections Issued | JACK KARGODORIAN |
| Green Building Final | 4/18/2025 | Not Ready for Inspection | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 4/18/2025 | SGSOV Approved | JACK KARGODORIAN |
| Smoke Detectors | 4/18/2025 | Approved | JACK KARGODORIAN |
| ELECTRICAL-Final | 5/16/2025 | Approved | JENNIFER RABUCHIN |
| Final | 5/16/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| Green Building Final | 5/16/2025 | Approved | JENNIFER RABUCHIN |
| HVAC-Final | 5/16/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 5/16/2025 | Approved | JENNIFER RABUCHIN |