517 1/4 S CHICAGO ST 90033
Certificate Information: 517 1/4 S CHICAGO ST 90033
- Application / Permit
- 24016-10000-19612
- Plan Check / Job No.
- B24LA11498
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert existing 2 car garage (427 sq ft) into an accessory dwelling unit per GCS 65852.2(e)(1)(D)
- Permit Issued
- Issued on 2/27/2025
- Issuing Office
- Current Status
- Issued on 2/27/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/17/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2024 | MANUEL MONTUFAR |
| Corrections Issued | 7/30/2024 | MANUEL MONTUFAR |
| Quality Review Completed | 7/31/2024 | EUGENE BARBEAU |
| Plan Check Approved | 11/13/2024 | MANUEL MONTUFAR |
| Issued | 2/27/2025 | APPLICANT |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/11/2024 | HUGO GARRIDO GARZA |
| Roof/Waste drainage to street | Cleared | 10/24/2024 | STEVE MELGAR |
| Sewer availability | Cleared | 10/24/2024 | STEVE MELGAR |
| Address approval | Cleared | 10/31/2024 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2024 | STEVE MELGAR |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Espino,, Manuel A; Lic. No.: C55526 | 12109 WOODRUFF AVE DOWNEY, CA 90241 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/8/2025 | Partial Inspection | FREDDIE RIVERA |
| PLUMBING-Rough | 7/8/2025 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 7/17/2025 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 9/3/2025 | Partial Inspection | FREDDIE RIVERA |
| Green Building Rough | 9/3/2025 | Partial Inspection | FREDDIE RIVERA |
| MERV13>=Rough | 9/3/2025 | Partial Inspection | FREDDIE RIVERA |
| METHANE-Rough | 9/3/2025 | Not Ready for Inspection | FREDDIE RIVERA |
| Special/Order Compliance | 9/3/2025 | Partial Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 11/6/2025 | Partial Approval | FREDDIE RIVERA |
| Pre-Inspection | 11/6/2025 | Corrections Issued | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 11/13/2025 | Partial Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 11/13/2025 | Approved | FREDDIE RIVERA |
| Green Building Rough | 11/13/2025 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 11/13/2025 | Partial Approval | FREDDIE RIVERA |
| MERV13>=Rough | 11/13/2025 | Approved | FREDDIE RIVERA |
| METHANE-Rough | 11/13/2025 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 11/13/2025 | Approved | FREDDIE RIVERA |
| Insulation | 11/25/2025 | Approved | FREDDIE RIVERA |
| Interior/Exterior Lathing | 11/25/2025 | Partial Approval | FREDDIE RIVERA |
| Drywall Nailing | 12/23/2025 | Approved | FREDDIE RIVERA |