456 S BREED ST 1-30 90033
Certificate Information: 456 S BREED ST 1-30 90033
- Application / Permit
- 24016-10000-19435
- Plan Check / Job No.
- B24LA11379
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERSION OF GARAGE AT FRONT AND REC. ROOM INTO 2 ADUs. CONVERT (E) TUCKED UNDER PARKING AT THE REAR OF BUILDING TO 4 ADUs (PER STATE CODE)
- Permit Issued
- Issued on 11/22/2024
- Issuing Office
- Current Status
- Issued on 11/22/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/17/2024 | APPLICANT |
| Assigned to Zoning Architect | 6/20/2024 | AMIR NAKHLA |
| Assigned to Plan Check Engineer | 7/3/2024 | JOE VO |
| Corrections Issued | 7/18/2024 | JOE VO |
| Quality Review Completed | 7/19/2024 | GARO TELMI |
| Applicant returned to address corrections | 9/16/2024 | JOE VO |
| Plan Check Approved | 11/5/2024 | JOE VO |
| Issued | 11/22/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/23/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2024 | DAVID LOPEZ |
| Highway dedication | Cleared | 7/23/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 7/23/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 7/23/2024 | DAVID LOPEZ |
| Miscellaneous | Cleared | 8/9/2024 | JOE VO |
| DAS Clearance | Cleared | 8/16/2024 | ANDY VUONG |
| Tenant Habitability Plan | Cleared | 9/4/2024 | RICARDO BOHORQUEZ |
| Grading Pre-Inspection | Cleared | 9/16/2024 | JOE VO |
| Miscellaneous | Cleared | 9/16/2024 | JOE VO |
| Hydrant and Access approval | Cleared | 9/19/2024 | JOHN CONNEALLY |
| Green Code | Cleared | 10/4/2024 | Rosendo Medina |
| Zoning Plan Check | Cleared | 10/8/2024 | Rosendo Medina |
| Fire Marshal Fire Life Safety | Cleared | 10/29/2024 | WILLIAM JOHNS |
Contact Information
| Contractor | L A Developing Inc; Lic. No.: 1083426-B | , |
| Engineer | Arutyunyan,, Vladimir; Lic. No.: NA92714 | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/12/2025 | Partial Approval | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2025 | Partial Inspection | RONALD JIMENEZ |
| Special/Order Compliance | 4/11/2025 | Approved | RONALD JIMENEZ |
| Wood Frame | 4/11/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/14/2025 | Partial Approval | RONALD JIMENEZ |
| Footing/Foundation/Slab | 4/18/2025 | Partial Approval | RONALD JIMENEZ |
| Green Building Rough | 5/13/2025 | Partial Approval | JEROME BLACKWOOD |
| METHANE-Rough | 5/13/2025 | Approved | JEROME BLACKWOOD |
| Wood Frame | 5/13/2025 | Partial Approval | JEROME BLACKWOOD |
| Footing/Foundation/Slab | 5/19/2025 | Approved | RONALD JIMENEZ |
| Wood Frame | 5/19/2025 | Partial Approval | RONALD JIMENEZ |
| Insulation | 5/23/2025 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 5/28/2025 | Partial Approval | RONALD JIMENEZ |
| Interior/Exterior Lathing | 5/28/2025 | Partial Approval | RONALD JIMENEZ |
| Green Building Rough | 7/10/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Wood Frame | 7/10/2025 | Not Ready for Inspection | RONALD JIMENEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Green Building Rough | 7/15/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 7/15/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2025 | Approved | RONALD JIMENEZ |
| Green Building Rough | 7/18/2025 | Approved | RONALD JIMENEZ |
| Wood Frame | 7/18/2025 | Approved | RONALD JIMENEZ |
| Insulation | 7/21/2025 | Approved | RONALD JIMENEZ |
| Drywall Nailing | 7/23/2025 | Approved | RONALD JIMENEZ |
| Interior/Exterior Lathing | 7/23/2025 | Partial Approval | RONALD JIMENEZ |
| Interior/Exterior Lathing | 7/24/2025 | Partial Approval | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 9/11/2025 | SGSOV Not Ready | RONALD JIMENEZ |
| Final | 6/18/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| Green Building Final | 6/18/2026 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 6/18/2026 | SGSOV Not Ready | JEROME BLACKWOOD |
| Smoke Detectors | 6/18/2026 | Not Ready for Inspection | JEROME BLACKWOOD |