6372 W SUNSET BLVD 90028
Certificate Information: 6372 W SUNSET BLVD 90028
- Application / Permit
- 24016-10000-19374
- Plan Check / Job No.
- B24LA11318
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- [ePlan]Partial Exterior and Full Interior remodel that consists of new finish, equipment, layout, bars, performance platforms,soffit framing, interior partition walls, new sound & lighting unit anchorage, and new storefront at the main entrance.
- Permit Issued
- Issued on 2/6/2025
- Issuing Office
- Current Status
- Permit Finaled on 11/20/2025
Permit Application Status History
| Submitted | 6/27/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2024 | SALVADOR QUINTANILLA |
| Assigned to Zoning Architect | 7/3/2024 | SALVADOR QUINTANILLA |
| Corrections Issued | 7/6/2024 | SALVADOR QUINTANILLA |
| Quality Review Completed | 7/9/2024 | PETER KIM |
| Applicant returned to address corrections | 7/15/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 9/27/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 10/3/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 10/10/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 10/23/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 10/31/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 11/6/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 11/8/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 11/19/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 12/6/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 12/9/2024 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/3/2025 | SALVADOR QUINTANILLA |
| Applicant returned to address corrections | 1/30/2025 | SALVADOR QUINTANILLA |
| Plan Check Approved | 2/5/2025 | SALVADOR QUINTANILLA |
| Issued | 2/6/2025 | APPLICANT |
| Permit Finaled | 11/19/2025 | RONALD JIMENEZ |
Permit Application Clearance Information
| Historic Resource Verification | Cleared | 7/10/2024 | RAFAEL FONTES |
| Redevelopment Project Area | Cleared | 7/18/2024 | YASMINE BASHIRI |
| Fire Marshal Fire Life Safety | Cleared | 12/1/2024 | FIRE DEPARTMENT |
| ZA Case | Cleared | 12/23/2024 | EDWIN CANO |
| Food Service Establishment | Cleared | 12/27/2024 | PAWAN VERMA |
| Food establishment approval | Cleared | 1/3/2025 | LACDHS APPROVED |
| DAS Clearance | Cleared | 1/28/2025 | Joseph Rafols |
| Zoning Plan Check | Cleared | 1/31/2025 | Joseph Rafols |
Contact Information
| Architect | Gallardo,, Conrado J; Lic. No.: NA29223 | , |
| Contractor | Owner-Builder | , |
| Engineer | Allen,, Thomas Christopher; Lic. No.: S5460 | 2 VENTURE, SUITE 200 IRVINE, CA 92618 |
Inspector Information
| TIMOTHY POWELL, (213) 482-0360 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/19/2025 | Approved | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 3/7/2025 | Partial Approval | TIMOTHY POWELL |
| Footing/Foundation/Slab | 3/7/2025 | Partial Approval | TIMOTHY POWELL |
| Excavation/Setback/Form/Re-Bar | 3/26/2025 | Approved | TIMOTHY POWELL |
| Light Gage Steel Frame | 4/3/2025 | Not Ready for Inspection | TIMOTHY POWELL |
| Light Gage Steel Frame | 4/3/2025 | Partial Approval | TIMOTHY POWELL |
| Drywall Nailing | 4/25/2025 | Partial Approval | MARTIN TAVITIAN |
| Footing/Foundation/Slab | 5/7/2025 | Partial Approval | TIMOTHY POWELL |
| Light Gage Steel Frame | 5/19/2025 | Partial Approval | TIMOTHY POWELL |
| Light Gage Steel Frame | 6/10/2025 | Partial Approval | TIMOTHY POWELL |
| T-Bar Ceiling | 6/24/2025 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 7/1/2025 | Partial Approval | PAUL BAZERKANIAN |
| T-Bar Ceiling | 7/9/2025 | Partial Approval | LUIS CCAMACHO |
| Light Gage Steel Frame | 7/14/2025 | Partial Approval | TIMOTHY POWELL |
| Final | 8/8/2025 | Corrections Issued | RONALD JIMENEZ |
| Final | 11/19/2025 | Permit Finaled | RONALD JIMENEZ |
| SGSOV-Seismic Gas S/O Valve | 11/19/2025 | SGSOV Approved | RONALD JIMENEZ |
| Smoke Detectors | 11/19/2025 | Approved | RONALD JIMENEZ |