855 W 83RD ST 90044
Certificate Information: 855 W 83RD ST 90044
- Application / Permit
- 24016-10000-19333
- Plan Check / Job No.
- B24LA11278
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan. CONVERT EXISTING GARAGE INTO AN ADU
- Permit Issued
- Issued on 9/16/2024
- Issuing Office
- Current Status
- CofO Issued on 4/30/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/20/2024 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 6/20/2024 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 7/14/2024 | FARSHAD ALIMOHAMADI |
| Issued | 9/16/2024 | APPLICANT |
| CofO in Progress | 4/28/2026 | JOHN QUINTANILLA |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
| CofO Issued | 4/30/2026 | DEROLD HAUFF |
| Permit Finaled | 4/30/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 7/9/2024 | DAVID VO |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2024 | DAVID VO |
| Sewer availability | Cleared | 7/9/2024 | DAVID VO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Gonzalez,, Fernando Francisco; Lic. No.: NA53256 | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/11/2024 | Conditional Approval | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2024 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 12/16/2024 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Rough | 12/18/2024 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 2/12/2025 | Partial Approval | JOSH MEISTER |
| BUILDING-Rough-Frame | 3/19/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 3/19/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 3/19/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 3/19/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 3/21/2025 | Approved | JOHN QUINTANILLA |
| Insulation | 3/24/2025 | Approved | JOHN QUINTANILLA |
| Drywall Nailing | 4/1/2025 | Corrections Issued | ANTHONY RAMOS |
| Drywall Nailing | 4/7/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 4/7/2025 | Approved | JOHN QUINTANILLA |
| Final | 1/15/2026 | Corrections Issued | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 1/15/2026 | SGSOV Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 1/15/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Final | 4/24/2026 | OK to Issue CofO | JOHN QUINTANILLA |
| Smoke Detectors | 4/24/2026 | Approved | JOHN QUINTANILLA |
| Service/Power Release | 4/28/2026 | Approved | JOHN QUINTANILLA |