3463 N WONDER VIEW PL 90068
Certificate Information: 3463 N WONDER VIEW PL 90068
- Application / Permit
- 24016-10000-19311
- Plan Check / Job No.
- B24LA11246
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- [ePlan] Interior remodel to existing basement and repair to (e) deck and existing exterior stairs
- Permit Issued
- Issued on 3/31/2025
- Issuing Office
- Current Status
- Permit Finaled on 5/11/2026
Permit Application Status History
| Submitted | 6/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 7/3/2024 | JAD BASMA |
| Corrections Issued | 7/10/2024 | JAD BASMA |
| Quality Review Completed | 7/26/2024 | MICHAEL PEREZ |
| Applicant returned to address corrections | 8/30/2024 | JAD BASMA |
| Plan Check Approved | 10/4/2024 | JAD BASMA |
| Issued | 3/31/2025 | APPLICANT |
| Permit Finaled | 5/8/2026 | ROY SPAULDING |
Permit Application Clearance Information
| ZA Case | Cleared | 7/24/2024 | NATHAN ROMINE |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2024 | CHRISTINA BRACO |
| Sewer availability | Cleared | 7/25/2024 | CHRISTINA BRACO |
| Grading Pre-Inspection | Cleared | 7/29/2024 | ALEXANDER HELFER |
| GPI Written Notices | Cleared | 10/4/2024 | JAD BASMA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| ROY SPAULDING, (213) 202-3461 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/29/2025 | Partial Inspection | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 5/15/2025 | Partial Approval | BRIAN SULLIVAN |
| Deputy Steel/Welding | 6/20/2025 | Conditional Approval | JOSH MEISTER |
| Deputy Steel/Welding | 6/27/2025 | Conditional Approval | DAVID WILLIAMS |
| Deputy Steel/Welding | 7/8/2025 | Conditional Approval | BRIAN SULLIVAN |
| Underground Mechanical | 7/25/2025 | Partial Approval | ROY SPAULDING |
| Deputy Drilled-In Anchors | 8/7/2025 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 8/7/2025 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 8/12/2025 | Corrections Issued | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 8/12/2025 | Not Ready for Inspection | BRIAN SULLIVAN |
| Piling/Pier/Caisson | 8/18/2025 | Approved | BRIAN SULLIVAN |
| Deputy Steel/Welding | 8/27/2025 | Conditional Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/9/2025 | Partial Approval | BRIAN SULLIVAN |
| HVAC-Rough | 9/9/2025 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 9/9/2025 | Corrections Issued | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/9/2025 | Corrections Issued | BRIAN SULLIVAN |
| Wood Frame | 9/9/2025 | Corrections Issued | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 9/22/2025 | Partial Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/22/2025 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/22/2025 | Approved | BRIAN SULLIVAN |
| Insulation | 9/29/2025 | Approved | BRIAN SULLIVAN |
| Drywall Nailing | 10/3/2025 | Approved | BRIAN SULLIVAN |
| Shower Pan | 10/3/2025 | Approved | BRIAN SULLIVAN |
| Shower Pan | 10/6/2025 | Approved | BRIAN SULLIVAN |
| ELECTRICAL-Final | 2/23/2026 | Approved | DAVID WILLIAMS |
| Final | 2/23/2026 | Corrections Issued | DAVID WILLIAMS |
| HVAC-Final | 2/23/2026 | Approved | DAVID WILLIAMS |
| PLUMBING-Final | 2/23/2026 | Approved | DAVID WILLIAMS |
| SGSOV-Seismic Gas S/O Valve | 2/23/2026 | SGSOV Approved | DAVID WILLIAMS |
| Smoke Detectors | 2/23/2026 | Approved | DAVID WILLIAMS |
| Final | 3/23/2026 | Not Ready for Inspection | DAVID WILLIAMS |
| Structural Steel Frame | 3/23/2026 | Approved | DAVID WILLIAMS |
| Interior/Exterior Lathing | 3/24/2026 | Approved | ROY SPAULDING |
| Final | 4/14/2026 | Corrections Issued | ROY SPAULDING |
| Final | 5/8/2026 | Permit Finaled | ROY SPAULDING |