1835 S HOLMBY AVE 1-17 90025
Certificate Information: 1835 S HOLMBY AVE 1-17 90025
- Application / Permit
- 24016-10000-19216
- Plan Check / Job No.
- B24LA11164
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERT (E) RECREATION ROOM AND ADJACENT COVERED PATIO AREA IN APARTMENT TO ATTACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(C). NFPA 13 FIRE SPRINKLER.
- Permit Issued
- Issued on 11/19/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 11/19/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/11/2024 | APPLICANT |
| Assigned to Zoning Architect | 6/13/2024 | LY CHEA |
| Assigned to Plan Check Engineer | 6/27/2024 | DANIEL YIP |
| Corrections Issued | 7/3/2024 | DANIEL YIP |
| Quality Review Completed | 7/12/2024 | KEN GILL |
| Plan Check Approved | 10/21/2024 | DANIEL YIP |
| Issued | 11/19/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2024 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 7/31/2024 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 8/8/2024 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 9/24/2024 | JOSHUA JONES |
| DAS Clearance | Cleared | 10/16/2024 | DANIEL YIP |
| Zoning Plan Check | Cleared | 10/17/2024 | LY CHEA |
Contact Information
| Architect | Zahabian,, Philip; Lic. No.: C23813 | 5237 NEWCASTLE AVE #307 ENCINO, CA 91316 |
| Contractor | Modern Blue Construction Inc; Lic. No.: 966004-B | 11838 BEL TERRACE LOS ANGELES, CA 90049 |
Inspector Information
| ROGELIO REYNA, (310) 914-3920 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/21/2025 | Not Ready for Inspection | RICARDO ROBLES |
| Footing/Foundation/Slab | 5/27/2025 | Approved | RICARDO ROBLES |
| METHANE-Final | 3/18/2026 | No Access for Inspection | CASIMIR BRITTON |
| METHANE-Rough | 3/18/2026 | No Access for Inspection | CASIMIR BRITTON |
| Wood Frame | 3/18/2026 | No Access for Inspection | CASIMIR BRITTON |
| METHANE-Final | 4/1/2026 | Approved | DANIEL VARNUM |
| METHANE-Rough | 4/1/2026 | Approved | DANIEL VARNUM |
| Wood Frame | 4/1/2026 | Approved | DANIEL VARNUM |
| Insulation | 4/6/2026 | Approved | DANIEL VARNUM |
| Drywall Nailing | 4/10/2026 | Approved | DANIEL ARMENTA |
| Interior/Exterior Lathing | 4/10/2026 | Approved | DANIEL ARMENTA |
| Final | 6/29/2026 | Not Ready for Inspection | DANIEL ARMENTA |
| SGSOV-Seismic Gas S/O Valve | 6/29/2026 | SGSOV Not Ready | DANIEL ARMENTA |
| Smoke Detectors | 6/29/2026 | Not Ready for Inspection | DANIEL ARMENTA |
| Final | 7/8/2026 | Partial Inspection | ROGELIO REYNA |
| SGSOV-Seismic Gas S/O Valve | 7/8/2026 | SGSOV No Gas | ROGELIO REYNA |
| Smoke Detectors | 7/8/2026 | Approved | ROGELIO REYNA |