3521 W LARGA AVE 90039

Certificate Information: 3521 W LARGA AVE 90039

Application / Permit
24016-10000-19071
Plan Check / Job No.
B24LA11066
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE AND STORAGE INTO A.D.U. PER STATE LAW.
Permit Issued
Issued on 10/17/2024
Issuing Office
Metro
Current Status
CofO Issued on 9/4/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2024 APPLICANT
Assigned to Plan Check Engineer 6/12/2024 LAWRENCE QUIRANTE
Corrections Issued 6/14/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 6/27/2024 APPLICANT
Plan Check Approved 10/17/2024 MINA HABILI
Issued 10/17/2024 APPLICANT
CofO in Progress 9/3/2025 NICHOLAS LOPEZ
Permit Finaled 9/4/2025 DEROLD HAUFF
Permit Finaled 9/4/2025 DEROLD HAUFF
CofO Issued 9/4/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 7/10/2024 CELINA MORENO
Sewer availability Cleared 7/10/2024 CELINA MORENO
Specific Plan Cleared 7/16/2024 YINGSHI HUANG
Eng Process Fee Ord 176,300 Cleared 7/17/2024 CELINA MORENO
Construction near power lines Cleared 10/9/2024 RIDWAN HARDY

Contact Information

Contractor Payne Diahanne Carolyn; Lic. No.: 686911-B 3371 GLENDALE BLVD 139      LOS ANGELES, CA 90039
Engineer Park,, Juntae; Lic. No.: C65104 3055 WILSHIRE BLVD 880      LOS ANGELES, CA 90010

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 11/22/2024 Partial Approval THOMAS LOGRASSO
Sewer 12/2/2024 Approved THOMAS LOGRASSO
Underground Mechanical 12/2/2024 Approved THOMAS LOGRASSO
Footing/Foundation/Slab 12/6/2024 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 12/26/2024 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 12/26/2024 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 1/3/2025 Not Ready for Inspection THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 1/7/2025 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 1/7/2025 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 1/7/2025 Conditional Approval THOMAS LOGRASSO
BUILDING-Rough-Frame 1/15/2025 Corrections Issued THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 1/15/2025 Corrections Issued THOMAS LOGRASSO
Insulation 1/22/2025 Not Ready for Inspection THOMAS LOGRASSO
Service/Power Release 5/23/2025 Corrections Issued NICHOLAS LOPEZ
Drywall Nailing 7/8/2025 Approved NICHOLAS LOPEZ
ELECTRICAL-Final 7/8/2025 Approved NICHOLAS LOPEZ
HVAC-Final 7/8/2025 Corrections Issued NICHOLAS LOPEZ
PLUMBING-Final 7/8/2025 Corrections Issued NICHOLAS LOPEZ
Pre-Inspection 7/8/2025 Partial Inspection NICHOLAS LOPEZ
Smoke Detectors 7/8/2025 Approved NICHOLAS LOPEZ
PLUMBING-Final 7/24/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 8/7/2025 Approved NICHOLAS LOPEZ
BUILDING-Rough-Frame 8/19/2025 Approved NICHOLAS LOPEZ
Final 8/19/2025 Corrections Issued NICHOLAS LOPEZ
Green Building Final 8/19/2025 Not Ready for Inspection NICHOLAS LOPEZ
Green Building Rough 8/19/2025 Approved NICHOLAS LOPEZ
SGSOV-Seismic Gas S/O Valve 8/19/2025 SGSOV Approved NICHOLAS LOPEZ
Final 9/2/2025 OK to Issue CofO NICHOLAS LOPEZ
Green Building Final 9/2/2025 Approved NICHOLAS LOPEZ