1501 N BENTON WAY 90026

Certificate Information: 1501 N BENTON WAY 90026

Application / Permit
24016-10000-19023
Plan Check / Job No.
B24LA10718
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN CONVERT (E) REC ROOM ABOVE DETACHED GARAGE INTO ADU PER CA Govt. Code 65852.2(e)(1)(A) (2 OF 2)
Permit Issued
Issued on 11/25/2024
Issuing Office
Current Status
Issued on 11/25/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/4/2024 APPLICANT
Assigned to Plan Check Engineer 6/7/2024 JOHNPAUL ISIP
Corrections Issued 6/9/2024 JOHNPAUL ISIP
Plan Check Approved 6/23/2024 REZA HAGHIGHAT
Issued 11/25/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 6/12/2024 JUSTIN BICOL
Sewer availability Cleared 6/12/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 6/13/2024 JUSTIN BICOL

Contact Information

Contractor Bg Construction & Remodeling Inc; Lic. No.: 817992-B 1360 WESTERN AVE      GLENDALE, CA 91201
Engineer Vahabzadeh,, Reza; Lic. No.: NA6538       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 12/17/2024 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/17/2024 Corrections Issued HAMIK HARTOUNIAN
HVAC-Rough 12/17/2024 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 12/17/2024 Corrections Issued HAMIK HARTOUNIAN
Wood Frame 12/17/2024 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 1/31/2025 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 1/31/2025 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 2/4/2025 Approved JOSH MEISTER
PLUMBING-Rough 2/4/2025 Approved JOSH MEISTER
Footing/Foundation/Slab 2/6/2025 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Rough 2/11/2025 Corrections Issued HAMIK HARTOUNIAN
Interior/Exterior Lathing 2/11/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Shower Pan 2/11/2025 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 2/20/2025 Approved SCOTT FINNILA
ELECTRICAL-Final 2/20/2025 Partial Inspection SCOTT FINNILA
Green Building Rough 2/20/2025 Approved SCOTT FINNILA
HVAC-Rough 2/20/2025 Approved SCOTT FINNILA
Drywall Nailing 3/3/2025 Partial Approval HAMIK HARTOUNIAN
Insulation 3/3/2025 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 3/3/2025 Approved HAMIK HARTOUNIAN
Pre-Inspection 4/28/2025 Partial Approval HAMIK HARTOUNIAN
Drywall Nailing 5/1/2025 Approved ALEX COLIN
ELECTRICAL-Final 8/22/2025 Not Ready for Inspection HAMIK HARTOUNIAN
Final 8/22/2025 Corrections Issued HAMIK HARTOUNIAN
HVAC-Final 8/22/2025 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 8/22/2025 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/22/2025 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 8/22/2025 Corrections Issued HAMIK HARTOUNIAN
Final 9/22/2025 Partial Inspection HAMIK HARTOUNIAN
Smoke Detectors 9/22/2025 Approved HAMIK HARTOUNIAN
Final 9/24/2025 Corrections Issued HAMIK HARTOUNIAN