1845 S COCHRAN PL 90019

Certificate Information: 1845 S COCHRAN PL 90019

Application / Permit
24016-10000-19009
Plan Check / Job No.
B24LA11043
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 20' X 27' DETACHED GARAGE INTO A.D.U. PER STATE LAW.
Permit Issued
Issued on 3/27/2025
Issuing Office
Metro
Current Status
CofO Issued on 12/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/10/2024 APPLICANT
Assigned to Plan Check Engineer 6/12/2024 LAWRENCE QUIRANTE
Corrections Issued 6/13/2024 LAWRENCE QUIRANTE
Building Plans Picked Up 7/12/2024 APPLICANT
Plan Check Approved 12/23/2024 NEHEMIAS RAMOS
Issued 3/27/2025 APPLICANT
CofO in Progress 12/24/2025 BRENDAN MORELLI
Permit Finaled 12/27/2025 DEROLD HAUFF
CofO Issued 12/27/2025 DEROLD HAUFF
Permit Finaled 12/27/2025 DEROLD HAUFF

Permit Application Clearance Information

Construction near power lines Cleared 11/3/2024 TINA MIRANDA
Address approval Cleared 11/9/2024 TREVOR QUAN
Sewer availability Cleared 11/9/2024 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 11/12/2024 TREVOR QUAN

Contact Information

Contractor Cr Builders Llc; Lic. No.: 1131278-B       ,
Engineer Lu,, Yi; Lic. No.: S5678 P O BOX 2754      PALOS VERDES PENINSULA, CA 90274

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/7/2025 Approved ARTHUR NEGRETE
Excavation/Setback/Form/Re-Bar 4/14/2025 Corrections Issued ARTHUR NEGRETE
Special/Order Compliance 4/14/2025 Partial Inspection ALEX COLIN
Underground Mechanical 4/14/2025 Approved ARTHUR NEGRETE
ELECTRICAL-Rough 6/4/2025 Approved ARTHUR NEGRETE
HVAC-Rough 6/4/2025 Approved ARTHUR NEGRETE
PLUMBING-Rough 6/4/2025 Approved ARTHUR NEGRETE
Sewer 6/4/2025 Approved ARTHUR NEGRETE
Underground Mechanical 6/4/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 6/9/2025 Approved ARTHUR NEGRETE
Rough-Elec/Plmb/HVAC 6/9/2025 Approved ARTHUR NEGRETE
Insulation 6/11/2025 Approved ARTHUR NEGRETE
Interior/Exterior Lathing 6/13/2025 Approved ARTHUR NEGRETE
Drywall Nailing 6/17/2025 Approved ARTHUR NEGRETE
BUILDING-Rough-Frame 12/4/2025 Approved BRENDAN MORELLI
ELECTRICAL-Final 12/4/2025 Corrections Issued BRENDAN MORELLI
Final 12/4/2025 Corrections Issued BRENDAN MORELLI
Green Building Final 12/4/2025 Partial Approval BRENDAN MORELLI
Green Building Rough 12/4/2025 Approved BRENDAN MORELLI
HVAC-Final 12/4/2025 Corrections Issued BRENDAN MORELLI
PLUMBING-Final 12/4/2025 Corrections Issued BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 12/4/2025 SGSOV Not Ready BRENDAN MORELLI
Smoke Detectors 12/4/2025 Approved BRENDAN MORELLI
ELECTRICAL-Final 12/19/2025 Corrections Issued WILLIAM SIERRA
Final 12/19/2025 Corrections Issued WILLIAM SIERRA
Green Building Final 12/19/2025 Approved WILLIAM SIERRA
HVAC-Final 12/19/2025 Approved WILLIAM SIERRA
PLUMBING-Final 12/19/2025 Approved WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 12/19/2025 SGSOV Approved WILLIAM SIERRA
ELECTRICAL-Final 12/23/2025 Approved BRENDAN MORELLI
Final 12/23/2025 OK to Issue CofO BRENDAN MORELLI
Service/Power Release 12/23/2025 Approved BRENDAN MORELLI