- CONVERT 20' X 27' DETACHED GARAGE INTO A.D.U. PER STATE LAW.
- Permit Issued
- Issued on 3/27/2025
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/12/2024 | LAWRENCE QUIRANTE |
| Corrections Issued | 6/13/2024 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 7/12/2024 | APPLICANT |
| Plan Check Approved | 12/23/2024 | NEHEMIAS RAMOS |
| Issued | 3/27/2025 | APPLICANT |
| CofO in Progress | 12/24/2025 | BRENDAN MORELLI |
| Permit Finaled | 12/27/2025 | DEROLD HAUFF |
| CofO Issued | 12/27/2025 | DEROLD HAUFF |
| Permit Finaled | 12/27/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 11/3/2024 | TINA MIRANDA |
| Address approval | Cleared | 11/9/2024 | TREVOR QUAN |
| Sewer availability | Cleared | 11/9/2024 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 11/12/2024 | TREVOR QUAN |
Contact Information
| Contractor | Cr Builders Llc; Lic. No.: 1131278-B | , |
| Engineer | Lu,, Yi; Lic. No.: S5678 | P O BOX 2754 PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/7/2025 | Approved | ARTHUR NEGRETE |
| Excavation/Setback/Form/Re-Bar | 4/14/2025 | Corrections Issued | ARTHUR NEGRETE |
| Special/Order Compliance | 4/14/2025 | Partial Inspection | ALEX COLIN |
| Underground Mechanical | 4/14/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Rough | 6/4/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Rough | 6/4/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Rough | 6/4/2025 | Approved | ARTHUR NEGRETE |
| Sewer | 6/4/2025 | Approved | ARTHUR NEGRETE |
| Underground Mechanical | 6/4/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 6/9/2025 | Approved | ARTHUR NEGRETE |
| Rough-Elec/Plmb/HVAC | 6/9/2025 | Approved | ARTHUR NEGRETE |
| Insulation | 6/11/2025 | Approved | ARTHUR NEGRETE |
| Interior/Exterior Lathing | 6/13/2025 | Approved | ARTHUR NEGRETE |
| Drywall Nailing | 6/17/2025 | Approved | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 12/4/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 12/4/2025 | Corrections Issued | BRENDAN MORELLI |
| Final | 12/4/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 12/4/2025 | Partial Approval | BRENDAN MORELLI |
| Green Building Rough | 12/4/2025 | Approved | BRENDAN MORELLI |
| HVAC-Final | 12/4/2025 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 12/4/2025 | Corrections Issued | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 12/4/2025 | SGSOV Not Ready | BRENDAN MORELLI |
| Smoke Detectors | 12/4/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 12/19/2025 | Corrections Issued | WILLIAM SIERRA |
| Final | 12/19/2025 | Corrections Issued | WILLIAM SIERRA |
| Green Building Final | 12/19/2025 | Approved | WILLIAM SIERRA |
| HVAC-Final | 12/19/2025 | Approved | WILLIAM SIERRA |
| PLUMBING-Final | 12/19/2025 | Approved | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 12/19/2025 | SGSOV Approved | WILLIAM SIERRA |
| ELECTRICAL-Final | 12/23/2025 | Approved | BRENDAN MORELLI |
| Final | 12/23/2025 | OK to Issue CofO | BRENDAN MORELLI |
| Service/Power Release | 12/23/2025 | Approved | BRENDAN MORELLI |