4500 N MAYCREST AVE 90032
Certificate Information: 4500 N MAYCREST AVE 90032
- Application / Permit
- 24016-10000-18554
- Plan Check / Job No.
- B24LA10755
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO (N) ADU PER STATE LAW
- Permit Issued
- Issued on 12/6/2024
- Issuing Office
- Metro
- Current Status
- Issued on 12/6/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2024 | JOSEPH RAFOLS |
| Corrections Issued | 6/7/2024 | JOSEPH RAFOLS |
| Building Plans Picked Up | 6/13/2024 | APPLICANT |
| Plan Check Approved | 12/6/2024 | SHANGQIN XIE |
| Issued | 12/6/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 6/27/2024 | JESSICA OPINION |
| Grading Pre-Inspection | Cleared | 7/25/2024 | MICHAEL TEMPLE |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2024 | AMY SHUM |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/28/2025 | Partial Inspection | LILIANA PORTILLO |
| Footing/Foundation/Slab | 2/24/2025 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 2/24/2025 | Partial Approval | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 4/3/2025 | Conditional Approval | LILIANA PORTILLO |
| Footing/Foundation/Slab | 4/7/2025 | Approved | ALIZAH MAYAGOITIA |
| Pre-Inspection | 10/21/2025 | Partial Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 3/12/2026 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 3/12/2026 | Corrections Issued | LILIANA PORTILLO |
| Wood Frame | 3/12/2026 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 4/3/2026 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 4/3/2026 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 4/16/2026 | Conditional Approval | LILIANA PORTILLO |
| HVAC-Rough | 4/16/2026 | Corrections Issued | LILIANA PORTILLO |
| Insulation | 4/23/2026 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 4/28/2026 | Approved | LILIANA PORTILLO |
| Insulation | 4/28/2026 | Partial Approval | LILIANA PORTILLO |
| Insulation | 5/8/2026 | Corrections Issued | ALEX COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2026 | Approved | NICHOLAS LOPEZ |
| Drywall Nailing | 6/3/2026 | Corrections Issued | GEM DE OCAMPO |
| Drywall Nailing | 6/5/2026 | No Result Entered | RONNIE MEDINA |