1503 N BENTON WAY 90026
Certificate Information: 1503 N BENTON WAY 90026
- Application / Permit
- 24016-10000-18497
- Plan Check / Job No.
- B24LA10718
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EPLAN REMODEL (E) 2 STORY SFD
- Permit Issued
- Issued on 9/26/2024
- Issuing Office
- Current Status
- Permit Finaled on 9/23/2025
Permit Application Status History
| Submitted | 6/4/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2024 | JOHNPAUL ISIP |
| Corrections Issued | 6/9/2024 | JOHNPAUL ISIP |
| Plan Check Approved | 6/23/2024 | REZA HAGHIGHAT |
| Issued | 9/26/2024 | APPLICANT |
| Permit Finaled | 9/22/2025 | HAMIK HARTOUNIAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Bg Construction & Remodeling Inc; Lic. No.: 817992-B | , |
| Engineer | Vahabzadeh,, Reza; Lic. No.: NA6538 | , |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 12/17/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/17/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Rough | 12/17/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/17/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| Wood Frame | 12/17/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 12/27/2024 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 12/27/2024 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 1/31/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Rough | 1/31/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| ELECTRICAL-Rough | 2/4/2025 | Approved | JOSH MEISTER |
| PLUMBING-Rough | 2/4/2025 | Approved | JOSH MEISTER |
| Footing/Foundation/Slab | 2/6/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/11/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 2/11/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Shower Pan | 2/11/2025 | Approved | HAMIK HARTOUNIAN |
| BUILDING-Rough-Frame | 2/20/2025 | Approved | SCOTT FINNILA |
| ELECTRICAL-Final | 2/20/2025 | Partial Inspection | SCOTT FINNILA |
| HVAC-Rough | 2/20/2025 | Partial Approval | SCOTT FINNILA |
| Interior/Exterior Lathing | 2/20/2025 | Partial Approval | SCOTT FINNILA |
| Drywall Nailing | 3/3/2025 | Approved | HAMIK HARTOUNIAN |
| Insulation | 3/3/2025 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 3/3/2025 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 3/14/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 8/22/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| Final | 8/22/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| HVAC-Final | 8/22/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 8/22/2025 | Approved | HAMIK HARTOUNIAN |
| SGSOV-Seismic Gas S/O Valve | 8/22/2025 | SGSOV Approved | HAMIK HARTOUNIAN |
| Smoke Detectors | 8/22/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 9/22/2025 | Permit Finaled | HAMIK HARTOUNIAN |
| Smoke Detectors | 9/22/2025 | Approved | HAMIK HARTOUNIAN |