1641 1/2 W 255TH ST 90710
Certificate Information: 1641 1/2 W 255TH ST 90710
- Application / Permit
- 24016-10000-17937
- Plan Check / Job No.
- B24LA10440
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: Convert existing detached garage into ADU per State Law.
- Permit Issued
- Issued on 9/8/2024
- Issuing Office
- Current Status
- CofO Issued on 6/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/7/2024 | RICARDO RAMIREZ |
| Corrections Issued | 6/8/2024 | RICARDO RAMIREZ |
| Plan Check Approved | 7/24/2024 | RICARDO RAMIREZ |
| Issued | 9/8/2024 | APPLICANT |
| CofO in Progress | 6/18/2025 | EUGENE CASSIDY |
| Permit Finaled | 6/20/2025 | ANSON MAGLASANG |
| CofO Issued | 6/20/2025 | ANSON MAGLASANG |
| Permit Finaled | 6/20/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2024 | JILVER MAZARIEGOS |
| Sewer availability | Cleared | 7/5/2024 | ERIK BEASLEY |
| Tenant Habitability Plan | Cleared | 7/9/2024 | HUGO GARRIDO GARZA |
| Eng Process Fee Ord 176,300 | Cleared | 7/23/2024 | JILVER MAZARIEGOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nagarajan,, Sivaram; Lic. No.: S6349 | 167 MATISSE CIRCLE ALISO VIEJO, CA 92656 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/3/2024 | Partial Approval | EUGENE CASSIDY |
| Sewer | 10/3/2024 | Approved | EUGENE CASSIDY |
| Deputy Drilled-In Anchors | 10/8/2024 | No Result Entered | BOB GOBUTY |
| Excavation/Setback/Form/Re-Bar | 10/9/2024 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 10/10/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 10/21/2024 | Partial Approval | EUGENE CASSIDY |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2024 | Partial Approval | EUGENE CASSIDY |
| METHANE-Rough | 10/21/2024 | Approved | EUGENE CASSIDY |
| BUILDING-Rough-Frame | 11/6/2024 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Rough | 11/6/2024 | Approved | EUGENE CASSIDY |
| HVAC-Rough | 11/6/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Rough | 11/6/2024 | Approved | EUGENE CASSIDY |
| Insulation | 11/21/2024 | Approved | EUGENE CASSIDY |
| Drywall Nailing | 11/27/2024 | Not Ready for Inspection | EUGENE CASSIDY |
| Interior/Exterior Lathing | 11/27/2024 | Partial Approval | EUGENE CASSIDY |
| Drywall Nailing | 12/3/2024 | Approved | EUGENE CASSIDY |
| Underground Mechanical | 3/4/2025 | Approved | EUGENE CASSIDY |
| Pre-Inspection | 3/17/2025 | Approved | EUGENE CASSIDY |
| Final | 5/28/2025 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/28/2025 | SGSOV Not Required | EUGENE CASSIDY |
| Service/Power Release | 5/28/2025 | Not Required | EUGENE CASSIDY |
| Smoke Detectors | 5/28/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| Service/Power Release | 6/12/2025 | Not Ready for Inspection | EUGENE CASSIDY |
| ELECTRICAL-Final | 6/18/2025 | Approved | EUGENE CASSIDY |
| Final | 6/18/2025 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 6/18/2025 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 6/18/2025 | Approved | EUGENE CASSIDY |
| Smoke Detectors | 6/18/2025 | Approved | EUGENE CASSIDY |