3956 W 6TH ST 90020
Certificate Information: 3956 W 6TH ST 90020
- Application / Permit
- 24016-10000-17931
- Plan Check / Job No.
- B24LA10434
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- EpLAN: Change of use from (e) retail to new restaurant. Tenant improvement to include new non bearing walls, new kitchen/serving area, new accessible restroom, and new finishes.
- Permit Issued
- Issued on 11/15/2024
- Issuing Office
- Current Status
- CofO Issued on 3/24/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/5/2024 | AUNG SOE |
| Corrections Issued | 6/7/2024 | AUNG SOE |
| Applicant returned to address corrections | 8/30/2024 | AUNG SOE |
| Applicant returned to address corrections | 11/6/2024 | AUNG SOE |
| Plan Check Approved | 11/6/2024 | AUNG SOE |
| Issued | 11/15/2024 | APPLICANT |
| CofO in Progress | 3/24/2026 | SEAN POMISH |
| Permit Finaled | 3/24/2026 | ERNESTO CORRAL |
| CofO Issued | 3/24/2026 | ERNESTO CORRAL |
| Permit Finaled | 3/24/2026 | ERNESTO CORRAL |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 8/28/2024 | ISMAEL HERNANDEZ |
| Miscellaneous | Cleared | 8/29/2024 | JAZMIN ROQUE |
| Specific Plan | Cleared | 8/29/2024 | JAZMIN ROQUE |
| Eng Process Fee Ord 176,300 | Cleared | 9/3/2024 | JOSE HERNANDEZ |
| ZA Case | Cleared | 9/24/2024 | RONY GIRON |
| Historic Resource Verification | Cleared | 9/25/2024 | YASMINE BASHIRI |
| Redevelopment Project Area | Cleared | 9/25/2024 | YASMINE BASHIRI |
| Food Service Establishment | Cleared | 10/10/2024 | PAWAN VERMA |
| Sewer availability | Cleared | 10/31/2024 | STEVE MELGAR |
| Public Works-Sewers | Cleared | 10/31/2024 | STEVE MELGAR |
| Food establishment approval | Cleared | 11/6/2024 | LACDHS APPROVED |
Contact Information
| Architect | , Jin Kyong Hur; Lic. No.: C38995 | 401 N SERRANO AVE PH2 LOS ANGELES, CA 90004 |
| Contractor | Jongwon Chung; Lic. No.: 1124928-B | , |
Inspector Information
| IAN BLINN, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRISTOPHER BLACKWOOD, (213) 482-7361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Light Gage Steel Frame | 2/5/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Pre-Inspection | 2/25/2025 | Not Ready for Inspection | MARTIN TAVITIAN |
| Drywall Nailing | 9/15/2025 | Partial Approval | PAUL BAZERKANIAN |
| Light Gage Steel Frame | 9/15/2025 | Partial Approval | PAUL BAZERKANIAN |
| Final | 3/24/2026 | OK to Issue CofO | SEAN POMISH |
| SGSOV-Seismic Gas S/O Valve | 3/24/2026 | SGSOV Approved | SEAN POMISH |
| Smoke Detectors | 3/24/2026 | Approved | SEAN POMISH |
| Wood Frame | 3/24/2026 | Approved | SEAN POMISH |