8323 S RAYFORD DR 90045
Certificate Information: 8323 S RAYFORD DR 90045
- Application / Permit
- 24016-10000-17777
- Plan Check / Job No.
- B24LA10350
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING 18'-0" X 20'-0" DETACHED GARAGE INTO ACCESSORY DWELLING UNIT PER GCS65852.2(e)(1)(A) ) - PER ENGINEER
- Permit Issued
- Issued on 7/17/2024
- Issuing Office
- Current Status
- CofO Issued on 11/5/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2024 | DANIEL ABRAMYAN |
| Corrections Issued | 6/4/2024 | DANIEL ABRAMYAN |
| Plan Check Approved | 7/2/2024 | DANIEL ABRAMYAN |
| Issued | 7/17/2024 | APPLICANT |
| CofO in Progress | 11/4/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 11/5/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/5/2024 | RICHARD STEINBACH |
| CofO Issued | 11/5/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2024 | DARIN LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2024 | DARIN LAM |
| Sewer availability | Cleared | 6/11/2024 | DARIN LAM |
| Specific Plan | Cleared | 6/11/2024 | RICHARD WOO |
| Grading Pre-Inspection | Cleared | 6/12/2024 | LANNY MERRICK |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Xi,, Wang; Lic. No.: NA85148 | , |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/13/2024 | Partial Inspection | BOBBY KEY |
| PLUMBING-Rough | 8/20/2024 | Partial Approval | BOBBY KEY |
| Sewer | 8/20/2024 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 8/23/2024 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Rough | 9/3/2024 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 9/3/2024 | Approved | BOBBY KEY |
| PLUMBING-Rough | 9/3/2024 | Approved | BOBBY KEY |
| BUILDING-Rough-Frame | 9/9/2024 | Partial Approval | BOBBY KEY |
| HVAC-Rough | 9/9/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 9/9/2024 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 9/12/2024 | Approved | BOBBY KEY |
| Insulation | 9/12/2024 | Corrections Issued | BOBBY KEY |
| Underground Mechanical | 9/12/2024 | Partial Approval | BOBBY KEY |
| Insulation | 9/16/2024 | Approved | BOBBY KEY |
| Shower Pan | 9/16/2024 | Approved | BOBBY KEY |
| Drywall Nailing | 9/18/2024 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 9/18/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 10/29/2024 | Corrections Issued | BOBBY KEY |
| Final | 10/29/2024 | Corrections Issued | BOBBY KEY |
| HVAC-Final | 10/29/2024 | Corrections Issued | BOBBY KEY |
| PLUMBING-Final | 10/29/2024 | Corrections Issued | BOBBY KEY |
| SGSOV-Seismic Gas S/O Valve | 10/29/2024 | SGSOV Approved | BOBBY KEY |
| Smoke Detectors | 10/29/2024 | Approved | BOBBY KEY |
| ELECTRICAL-Final | 11/1/2024 | Approved | TEMISTOCLES CAAL |
| Final | 11/1/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| HVAC-Final | 11/1/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 11/1/2024 | Approved | TEMISTOCLES CAAL |