1155 S ELDEN AVE 104 90006

Certificate Information: 1155 S ELDEN AVE 104 90006

Application / Permit
24016-10000-17769
Plan Check / Job No.
B24LA10341
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
EPLAN CONVERSION OF TWO PARKING GARAGE AND STORAGE ROOM INTO AN ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(C).
Permit Issued
Issued on 12/16/2024
Issuing Office
Current Status
CofO Issued on 12/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2024 APPLICANT
Assigned to Plan Check Engineer 5/30/2024 MICHAEL LOPEZ
Assigned to Zoning Architect 6/4/2024 ELHAM MADADVAND
Corrections Issued 6/9/2024 MICHAEL LOPEZ
Quality Review Completed 7/3/2024 MICHAEL PEREZ
Applicant returned to address corrections 11/12/2024 MICHAEL LOPEZ
Plan Check Approved 11/21/2024 MICHAEL LOPEZ
Plan Check Approved 12/11/2024 MICHAEL LOPEZ
Issued 12/16/2024 APPLICANT
CofO in Progress 10/16/2025 JEROME BLACKWOOD
CofO in Progress 12/17/2025 ERNESTO CORRAL
Permit Finaled 12/17/2025 ERNESTO CORRAL
CofO Issued 12/17/2025 ERNESTO CORRAL
Permit Finaled 12/17/2025 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 7/23/2024 WALLIE JONG
Sewer availability Cleared 7/23/2024 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 7/25/2024 WALLIE JONG
Fire Marshal Fire Life Safety Cleared 8/30/2024 WILLIAM JOHNS
Green Code Cleared 9/5/2024 AARON COSTA
Hydrant and Access approval Cleared 10/9/2024 JERRY KAO
Zoning Plan Check Cleared 11/6/2024 ELHAM MADADVAND

Contact Information

Contractor Moshe M Ben Porat; Lic. No.: 963181-B P O BOX 48603      LOS ANGELES, CA 90048
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

JEROME BLACKWOOD, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI
REGINA MENDEZ, (213) 213-5353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 2/14/2025 Approved JEROME BLACKWOOD
Footing/Foundation/Slab 2/14/2025 Partial Approval JEROME BLACKWOOD
Green Building Rough 3/25/2025 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 3/25/2025 Not Ready for Inspection JEROME BLACKWOOD
Green Building Rough 4/3/2025 Not Ready for Inspection JEROME BLACKWOOD
Wood Frame 4/3/2025 Not Ready for Inspection JEROME BLACKWOOD
Insulation 4/9/2025 Approved JEROME BLACKWOOD
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Approved JEROME BLACKWOOD
Drywall Nailing 4/22/2025 Partial Approval JEROME BLACKWOOD
Interior/Exterior Lathing 4/22/2025 Approved JEROME BLACKWOOD
Drywall Nailing 4/30/2025 Approved JEROME BLACKWOOD
Final 7/14/2025 Not Ready for Inspection JEROME BLACKWOOD
Green Building Final 7/14/2025 Approved JEROME BLACKWOOD
Green Building Rough 7/14/2025 Approved JEROME BLACKWOOD
SGSOV-Seismic Gas S/O Valve 7/14/2025 SGSOV Approved JEROME BLACKWOOD
Smoke Detectors 7/14/2025 Approved JEROME BLACKWOOD
Wood Frame 7/14/2025 Approved JEROME BLACKWOOD
Final 7/31/2025 Not Ready for Inspection PAUL BAZERKANIAN
Final 8/4/2025 Corrections Issued JEROME BLACKWOOD
Final 10/16/2025 OK to Issue CofO JEROME BLACKWOOD