404 1/2 W 95TH ST 90003
Certificate Information: 404 1/2 W 95TH ST 90003
- Application / Permit
- 24016-10000-17605
- Plan Check / Job No.
- B24LA10224
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- E-plan. Converting existing detached garage (1947LA00124) into ADU.
- Permit Issued
- Issued on 8/20/2024
- Issuing Office
- Current Status
- CofO Issued on 4/18/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2024 | JOSEPH RAFOLS |
| Corrections Issued | 7/31/2024 | SUNMIN LEE |
| Plan Check Approved | 8/19/2024 | SUNMIN LEE |
| Issued | 8/20/2024 | APPLICANT |
| CofO in Progress | 4/17/2025 | BEN MOLSTAD |
| Permit Finaled | 4/18/2025 | ANSON MAGLASANG |
| CofO Issued | 4/18/2025 | ANSON MAGLASANG |
| Permit Finaled | 4/18/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 6/25/2024 | DAVID LOPEZ |
| Eng Process Fee Ord 176,300 | Cleared | 6/26/2024 | DAVID LOPEZ |
| Sewer availability | Cleared | 7/22/2024 | DAVID LOPEZ |
| Construction near power lines | Cleared | 8/9/2024 | EDGAR PASCUA |
Contact Information
| Contractor | Y F General Construction Inc; Lic. No.: 1093812-B | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 9/19/2024 | Conditional Approval | ANSON MAGLASANG |
| Footing/Foundation/Slab | 9/23/2024 | Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 9/26/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2024 | Partial Approval | BEN MOLSTAD |
| Green Building Rough | 9/26/2024 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Rough | 9/26/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Gas Test | 10/15/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 10/15/2024 | Partial Approval | BEN MOLSTAD |
| Sewer | 10/15/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 10/16/2024 | Partial Approval | BEN MOLSTAD |
| Interior/Exterior Lathing | 10/24/2024 | Partial Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 10/24/2024 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 10/31/2024 | Corrections Issued | ANTHONY EGSON |
| Shower Pan | 11/4/2024 | Approved | BEN MOLSTAD |
| HVAC-Rough | 11/8/2024 | Approved | BEN MOLSTAD |
| PLUMBING-Rough | 11/8/2024 | Approved | BEN MOLSTAD |
| Interior/Exterior Lathing | 11/21/2024 | Approved | BEN MOLSTAD |
| ELECTRICAL-Rough | 12/10/2024 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 12/11/2024 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Rough | 12/11/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 12/11/2024 | Approved | BEN MOLSTAD |
| MERV13>=Rough | 12/11/2024 | Approved | BEN MOLSTAD |
| Wood Frame | 12/11/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Rough | 12/12/2024 | Approved | BEN MOLSTAD |
| Insulation | 12/16/2024 | Approved | BEN MOLSTAD |
| Drywall Nailing | 12/23/2024 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 2/25/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 2/25/2025 | Corrections Issued | BEN MOLSTAD |
| Final | 2/25/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 2/25/2025 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 2/25/2025 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Final | 2/25/2025 | Not Ready for Inspection | BEN MOLSTAD |
| PLUMBING-Final | 2/25/2025 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 2/25/2025 | SGSOV Not Ready | BEN MOLSTAD |
| Smoke Detectors | 2/25/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 4/7/2025 | Not Ready for Inspection | BEN MOLSTAD |
| Final | 4/7/2025 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 4/7/2025 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 4/7/2025 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Final | 4/7/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 4/7/2025 | Not Ready for Inspection | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 4/7/2025 | SGSOV Not Ready | BEN MOLSTAD |
| ELECTRICAL-Final | 4/9/2025 | Corrections Issued | BEN MOLSTAD |
| HVAC-Final | 4/9/2025 | Approved | BEN MOLSTAD |
| PLUMBING-Final | 4/9/2025 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 4/16/2025 | Order to Comply Issued | BEN MOLSTAD |
| Final | 4/16/2025 | OK to Issue CofO | BEN MOLSTAD |
| Green Building Final | 4/16/2025 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 4/16/2025 | SGSOV Approved | BEN MOLSTAD |