1675 E 97TH ST 90002
Certificate Information: 1675 E 97TH ST 90002
- Application / Permit
- 24016-10000-17451
- Plan Check / Job No.
- B24LA10107
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- EPLAN - split 1 unit of 4 unit apartment to 1 unit and 1 attached ADU resulting in 4 units and 1 attached ADU per LAMC 12.22 A.33 (c)(e) R2/U occupancy
- Permit Issued
- Issued on 9/30/2024
- Issuing Office
- Current Status
- CofO Issued on 1/30/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2024 | KELVIN CHUONG |
| Corrections Issued | 6/4/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 6/26/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 7/3/2024 | KELVIN CHUONG |
| Applicant returned to address corrections | 7/11/2024 | KELVIN CHUONG |
| Plan Check Approved | 8/7/2024 | KELVIN CHUONG |
| Issued | 9/30/2024 | APPLICANT |
| Permit Finaled | 1/30/2025 | WINSTON DUNNING |
| CofO Issued | 1/30/2025 | WINSTON DUNNING |
| Permit Finaled | 1/30/2025 | WINSTON DUNNING |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2024 | DAVID LOPEZ |
| Roof/Waste drainage to street | Cleared | 6/27/2024 | DAVID LOPEZ |
| Metro Rail approval | Cleared | 7/2/2024 | JENNIFER SU |
| Eng Process Fee Ord 176,300 | Cleared | 7/3/2024 | JEANIE LAM |
| Sewer availability | Cleared | 7/31/2024 | TREVOR QUAN |
Contact Information
| Contractor | Uribe Construction Llc; Lic. No.: 1029126-B | , |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 10/4/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Wood Frame | 10/9/2024 | Corrections Issued | DARRYL ARNOLD |
| Special/Order Compliance | 10/16/2024 | Approved | DARRYL ARNOLD |
| Final | 12/3/2024 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/3/2024 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 12/3/2024 | Approved | DARRYL ARNOLD |
| Wood Frame | 12/3/2024 | Approved | DARRYL ARNOLD |