12671 W VICTORIA AVE 90066

Certificate Information: 12671 W VICTORIA AVE 90066

Application / Permit
24016-10000-17443
Plan Check / Job No.
B24LA10098
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan - Convert detached garage into an Accessory Dwelling Unit per GCS 65852.2(e)(1)(A).
Permit Issued
Issued on 8/14/2024
Issuing Office
Current Status
CofO Issued on 12/31/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/3/2024 APPLICANT
Assigned to Plan Check Engineer 6/7/2024 PINANK PATEL
Corrections Issued 6/10/2024 PINANK PATEL
Plan Check Approved 6/15/2024 PINANK PATEL
Issued 8/14/2024 APPLICANT
CofO in Progress 12/26/2024 BOBBY KEY
Permit Finaled 12/31/2024 RICHARD STEINBACH
CofO Issued 12/31/2024 RICHARD STEINBACH
Permit Finaled 12/31/2024 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 6/12/2024 DIANA RENTERIA
Sewer availability Cleared 6/12/2024 DIANA RENTERIA
Eng Process Fee Ord 176,300 Cleared 6/13/2024 VLADIMIR ARUTYUNYAN
Grading Pre-Inspection Cleared 6/13/2024 CHARLES POWELL

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Value Up Renovation & Construction; Lic. No.: 1031128-B       ,

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/20/2024 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 9/20/2024 Approved JESUS PINEDA
Pre-Inspection 9/20/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 10/7/2024 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Rough 10/7/2024 Corrections Issued JESUS PINEDA
Excavation/Setback/Form/Re-Bar 10/7/2024 Approved JESUS PINEDA
HVAC-Rough 10/7/2024 Approved JESUS PINEDA
PLUMBING-Rough 10/7/2024 Approved JESUS PINEDA
Sewer 10/7/2024 Approved JESUS PINEDA
Underground Mechanical 10/7/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 10/15/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 10/15/2024 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/15/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 10/15/2024 Partial Approval JESUS PINEDA
Shower Pan 10/15/2024 Approved JESUS PINEDA
Insulation 10/21/2024 Approved MICHAEL ALLEN
Interior/Exterior Lathing 10/21/2024 Approved MICHAEL ALLEN
Drywall Nailing 10/25/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 11/8/2024 Approved JESUS PINEDA
Underground Mechanical 11/8/2024 Approved JESUS PINEDA
Final 12/20/2024 OK to Issue CofO BOBBY KEY
SGSOV-Seismic Gas S/O Valve 12/20/2024 SGSOV Approved BOBBY KEY
Smoke Detectors 12/20/2024 Approved BOBBY KEY
Special/Order Compliance 12/20/2024 Partial Inspection JAYLIN GRAVITTE