1211 N WETHERLY DR 90069

Certificate Information: 1211 N WETHERLY DR 90069

Application / Permit
24016-10000-17343
Plan Check / Job No.
B24LA10030
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**ePlan** Interior Structural Remodel of (E) SFD w/ attached Garage; scope of work to include: Relocation of existing bathroom/closets and the conversion of an existing closet into a new bathroom.
Permit Issued
Issued on 5/4/2025
Issuing Office
Current Status
Permit Finaled on 10/22/2025

Permit Application Status History

Submitted 6/5/2024 APPLICANT
Assigned to Plan Check Engineer 6/7/2024 EDWIN ESPIN
Corrections Issued 6/8/2024 EDWIN ESPIN
Applicant returned to address corrections 1/15/2025 AMY GUEVARRA
Applicant returned to address corrections 1/17/2025 AMY GUEVARRA
Plan Check Approved 1/21/2025 AMY GUEVARRA
Issued 5/4/2025 APPLICANT
Permit Finaled 10/21/2025 ROY SPAULDING

Permit Application Clearance Information

Grading Pre-Inspection Cleared 7/9/2024 GERMAN RODRIGUEZ MENDO

Contact Information

Contractor Thank You Construction Inc; Lic. No.: 1055452-B       ,
Engineer Phillips,, Craig; Lic. No.: NA69673       ,

Inspector Information

BRENDAN MORELLI, (213) 202-3412 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/9/2025 Approved BRENDAN MORELLI
HVAC-Rough 6/11/2025 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 6/11/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Rough 6/13/2025 Corrections Issued RAUL BARAJAS
HVAC-Rough 6/13/2025 Corrections Issued RAUL BARAJAS
Insulation 6/13/2025 Partial Approval RAUL BARAJAS
BUILDING-Rough-Frame 6/17/2025 Partial Approval ROY SPAULDING
ELECTRICAL-Rough 6/17/2025 Approved ROY SPAULDING
HVAC-Rough 6/17/2025 Approved ROY SPAULDING
Deputy Drilled-In Anchors 6/18/2025 Conditional Approval ROY SPAULDING
Deputy Wood Construction 6/18/2025 Conditional Approval ROY SPAULDING
Deputy Wood Construction 6/20/2025 Conditional Approval REGINA MENDEZ
BUILDING-Rough-Frame 6/24/2025 Approved JOSH MEISTER
Insulation 6/24/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 6/24/2025 Not Ready for Inspection JOSH MEISTER
Drywall Nailing 6/27/2025 Not Ready for Inspection JOSH MEISTER
Interior/Exterior Lathing 6/27/2025 Partial Approval JOSH MEISTER
Shower Pan 6/27/2025 Approved JOSH MEISTER
Drywall Nailing 6/30/2025 Approved JOSH MEISTER
Interior/Exterior Lathing 6/30/2025 Approved JOSH MEISTER
Deputy Drilled-In Anchors 9/11/2025 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 9/11/2025 Partial Approval CRAIG VAUGHAN
PLUMBING-Final 9/11/2025 Not Ready for Inspection CRAIG VAUGHAN
Masonry Wall/Backfill 9/16/2025 Approved ROY SPAULDING
ELECTRICAL-Final 10/8/2025 Corrections Issued ROY SPAULDING
Final 10/8/2025 Not Ready for Inspection ROY SPAULDING
Green Building Final 10/8/2025 Approved ROY SPAULDING
HVAC-Final 10/8/2025 Approved ROY SPAULDING
PLUMBING-Final 10/8/2025 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 10/8/2025 SGSOV Not Ready ROY SPAULDING
Smoke Detectors 10/8/2025 Approved ROY SPAULDING
ELECTRICAL-Final 10/21/2025 Approved ROY SPAULDING
Final 10/21/2025 Permit Finaled ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV Approved ROY SPAULDING